Amstetten
Location: Austria
Operator: SWH-Strom und Warme aus Holz Heizwerke
Configuration: 1 X 5 MW CHP
Operation: 2006
Fuel: wood
Boiler supplier: Urbas
T/G supplier: MAN
EPC: Urbas
Quick facts: Amstetten was commissioned in the summer of 2006 as a joint
venture of SWH and Umdasch AG, a manufacturer of shopfittings which will
supply about a third of the total fuel supply from waste timber products.
Österreichische Bundesforste AG, will provide the balance with chipped forestry residues. Annual output is
expected to be 40,000 MWh of electricity and 80,000 MWh of heat, of which about 65% will
be delivered to Umdasch and the remaining portion delivered to the
district heating network.
Photograph courtesy of SWH-Strom und Warme aus Holz Heizwerke
Posted 27 May 2009 |
FeuerWerk
Location: Austria
Operator: Binderholz GmbH
Configuration: 1 X 8.76 MW CHP
Operation: 2005
Fuel: wood chips, sawdust
Boiler supplier: Weiss
T/G supplier: B+V
Quick facts: This sawmill and power plant has extensive facilities for
tours and conferences. Helmut Reitter was the architect and designed
numerous special features to facilitate both activities. The plant cost
€30mn and is expected to produce about 56 GWh/yr of
electricity and 114 GWh/yr of heat.
Photograph courtesy of
Binderholz GmbH
Posted 28 Jun 2009 |
Fundermax
Location: Austria
Operator: FunderMax GmbH
Configuration: 1 X 10 MW CHP
Operation: 1983
Fuel: wood
Boiler supplier: AET
T/G supplier: Siemens
EPC: AET
Quick facts: This CHP plant si at a chipbioard plant and burns about
100,000 tpy of waste wood. AET supplied and installed the spreader stoker
combustion system and auxiliaries plus the APC equipment and installed these
items plus the stack and BOP equipment.
Photograph courtesy of Aalborg Energie Technik a/s
Posted 9 Jan 2011
|
|
Kleindöttingen
Location: Switzerland
Operator: Proma Energie AG
Configuration: 1 X 1.6 MW CHP
Operation: 2003
Fuel: wood
Boiler supplier: ??
T/G supplier: ??
Quick facts: This power station began operation in 1972 as a heat-only
facility. In 1996, the air-pollution control equipment was upgraded and in
1993, a steam T/G set was added to allow for CHP operation.
Photograph courtesy of Proma Energie AG
Posted 29 Dec 2007 |
Linz Mitte
Location: Austria
Operator: Linz AG
Configuration: 1 X 8.9 MW CHP
Operation: 2005
Fuel: wood
Boiler supplier: AET
T/G supplier: B+V
EPC: AET, Bascom
Quick facts: The first units at Linz Mitte went online in 1970.
These have now been retired and replaced by a 105-MW combined-cycle block
in 2004 and the new biomass power plant. One of the world's largest
thermal water storage tanks was also built.
Photograph courtesy of Linz
AG
Posted 22 Mar 2006 |
Zeltweg
Location: Austria
Operator: SWH-Strom und Warme aus Holz Heizwerke
Configuration: 1 X 1.5 MW CHP
Operation: 2006
Fuel: wood
Boiler supplier: Kohlbach
ORC supplier: Turboden
EPC: SWH
Quick facts: This ORC CHP is located at the pellets plant of Pellets-
und Leimbinderunternehmen Papst. Total heating
outpu it up to 9 MWt. The CHP plant runs the drying operation and the
sawdust band dryer for sawdust
Photograph courtesy of SWH-Strom und Warme aus Holz Heizwerke
Posted 3 Jul 2010 |