Biomass Power Plants in Thailand

Bang Mun Nak
Location: Pichit
Operator: AT Biopower Co Ltd

Configuration: 1 X 22 MW
Operation: 2005
Fuel: rice husk
Boiler supplier: McBurney
T/G supplier: Shin Nippon, Elin
Quick facts: This facility is in Bang Mun Nak District, Pichit Province, and went commercial on 21 Dec 2005. The plant burns about 150,000 tpy of rice husk and has a 25 yr PPA with EGAT under Thailand's Small Power Producer (SPP) program. The plant cost about 1,400mn Baht. The McBurney suspension firing system was the first-ever installation for a rice-husk fueled power plant. Project investors include Chubu Electric Power Co, Al Tayyar Energy, Private Energy Market Fund, Finnish Fund for Industrial Cooperation, Flagship Asia Corp, and Rolls-Royce Power Ventures. The plant received financial support of 900mn Baht from TMB Bank and Siam City Bank.

Photograph courtesy of Electrowatt-Ekono
Posted 25 Feb 2009

Burirum
Location: Buri Ram
Operator: Advance Bio Power Co Ltd

Configuration: 1 X 9.5 MW
Operation: 2007
Fuel: rice husk
Boiler supplier: Veesons
T/G supplier: ??
Quick facts: This is the first power plant in Thailand designed to burn 100% eucalyptus bark and chips obtained from nearby sawmills. The Danish Energy Agency supported this CDM project.

Photograph courtesy of Danish Energy Agency
Posted 29 Apr 2009

 

CGC Plant
Location: Nakhon Ratchasima
Operator: C Gigantic Carbon Co Ltd
Configuration: 1 X 2.76 MW CHP
Operation: ??
Fuel: biomass
Boiler supplier: ??
T/G supplier: ??
Quick facts: This is a captive power plant at Thailand's largest manufacturer of activated carbon using coconut shell and wood as raw materials

Photograph courtesy of C Gigantic Carbon Co
Posted 28 Jun 2009

 

Roi Et
Location: Roi Et
Operator:
Electricity Generating Public Co Ltd
Configuration: 1 X 9.8 MW
Operation: 2006
Fuel: rice husk
Boiler supplier: Yoshimine Co Ltd
T/G supplier: Shin Nippon, Meidensha
Quick facts: This biomass power plant is designed to burn 300t of rice husk per day and has a 21yr PPA with EGAT under Thailand's SPP scheme. The project received financial support from the Industrial Finance Corp of Thailand (IFCT) and the Office of Board of Investment (BOI). J-Power was an engineering consultant.

Photograph courtesy of Electricity Generating Public Co Ltd
Posted 17 Dec 2003

Surin MGP
Location: Prasart Surin
Operator: Mungcharoen Green Power Co Ltd
Configuration: 1 X 9.9 MW
Operation: 2007
Fuel: rice husk
Boiler supplier: ??
T/G supplier: ??
Quick facts: This plant was commissioned in Jan 2007. The SPP cost THB 550mn and took 2yrs to build. The plant fuel is about 85,000 tpy of rice husk supplied by farmers within a 30km radius of the plant site. MGP is the first large-scale, rice husk-based power plant project developed, invested, implemented, operated and maintained exclusively by a group of local rice millers and has a 21yr PPA contract with EGAT. The plant is directly connected to PEA’s 22kV grid The owners invested THB 150mn while THB 400mn was loaned by Bankthai Public Co Ltd and the Department of Alternative Energy Development and Efficiency (DEDE).

Photograph courtesy of Mungcharoen Green Power Co Ltd
Posted 17 Jun 2009