CCGT Plants in Austria
Donaustadt-3
Location: WIEN
Operator: Wienstrom
Configuration: 367-MW single-shaft CCGT with V94.3A gas turbine CHP
Fuel: natural gas
Operation: 2001
HRSG supplier: Danubius
T/G supplier: Siemens

Photograph courtesy of Wienstrom
Posted 15 Dec 2004

Leopoldau
Location: WIEN
Operator: Wienstrom
Configuration: 155-MW 1+1 CCGT block with V94 gas turbine CHP
Fuel: natural gas
Operation: 1976-1987
HRSG supplier: Biro
T/G supplier: Siemens, SGP
Quick facts: Leopoldau has what is considered the first SCR installed on a European combined-cycle, built in 1988.

Photograph courtesy of Wienstrom
Posted 18 Dec 2004

Mellach CC
Location: STM
Operator: Verbund Thermal Power GmbH & Co KG
Configuration: 2 X 419-MW, single-shaft CCGT blocks with SCC5-4000F gas turbines CHP
Fuel: natural gas
Operation: 2012
HRSG supplier: AEE
T/G supplier: Siemens
EPC: Siemens, Zorn & Nowy ZT GmbH, convex ZT GmbH, STRABAG-Porr
Quick facts: The Mellach CCGT project was officially handed-over on 22 Jun 2012, having started operations in May 2012. The thermal efficiency is reported at 59.2%, but with 400 MWt in district heating output, total efficiency is on the order of 80% making Mellach CC the largest and most efficient thermal power plant in Austria. To comply with local water usage restrictions, the plant features two different cooling systems: Unit-10 has a once-through system and Unit-20 has a cooling tower. The two transformers were manufactured and installed by the Siemens Transformers facility in Weiz.

Photograph courtesy of Siemens
Posted 23 Jun 2012

 
Salzburg Mitte
Location: SBG
Operator: Salzburger Stadtwerke AG
Configuration: 85-MW, 1+1 CCGT with GT8C2 gas turbine CHP
Fuel: natural gas
Operation: 2001-2002
HRSG supplier: Alstom
T/G supplier: ABB, Siemens

Photograph courtesy of Salzburger Stadtwerke AG
Posted 8 May 2004

Timelkam CC
Location: OOE
Operator: Gas- und Dampfkraftwerk Timelkam GmbH
Configuration: 405-MW, single-shaft CCGT with SCC5-4000F gas turbine
Fuel: natural gas
Operation: 2008
HRSG supplier: Balcke Dürr
T/G supplier: Siemens
EPC: Siemens, HGW Ingenieurgesellschaft mbH
Quick facts: The plant operating company is a joint venture of Energie AG Oberösterreich Kraftwerke GmbH and Groupe E SA. The plant was built in 25mos and has a design thermal efficiency of 59%.

Photograph courtesy of Energie AG Oberösterreich
Posted 5 May 2009

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 24-Oct-2012