CCGT Plants in Peru
Photograph courtesy of Kallpa Generacion SA
Photograph courtesy of Suez
Photograph courtesy of ABB
Photograph courtesy of Empresa de Generacion Arequipa SA
Photograph courtesy of Grupo Energetico Aguaytia
Photograph courtesy of Endesa Data: industcards, Platts UDI World Electric Power Plants Data Base



Chilca Kallpa
Location: Canete
Operator: Kallpa Generacion SA
Configuration: 1 X 180 MW W501FD3, 1 X 194 MW SGT6-5000F, 1 X 196 MW
SGT6-5000F gas turbines
Fuel: natural gas
Operation: 2007-2010
T/G supplier: Siemens
EPC: Worley, Inkia
Quick facts: Kallpa Generacion was founded as Globeleq Peru in 2005. In
Jun 2007 Inkia Energy, a subsidiary of Israel Corp, acquired Globeleq
assets in Latin America and the Caribbean. In Nov 2009, Quimpac SAA
acquired a 25.1% stake in Kallpa Generacion. The power station uses gas
from the Camisea fields. Uni-1 went online on 1 Jul 2007, followed by
Unit-2 in Jun 2009, and Unit-3 in Mar 2010. Kallpa is to be converted to
combined-cycle operation in 2012, at which point it will be the largest
thermal power plant in the country.
Posted 14 Jul 2010
ChilcaUno
Location: Canete
Operator: Suez EnerSur
Configuration: 2 X 174 MW V84.3A gas turbines
Fuel: natural gas
Operation: 2006-2007
T/G supplier: Siemens
EPC: Siemens
Quick facts: Fifteen months after the "Notice to
Proceed," Peruvian President Alan García Pérez and SUEZ Energy International CEO
Dirk Beeuwsaert inaugurated Chilca, the first dedicated power plant to use
gas from the Camisea field. The new plant is 64km south of Lima
and connected to the grid via a new 220kV substation and tie-line. A
second identical machine was commissioned on 8 Aug 2007. The total
investment required for both units was about $120mn.
Re-posted 15 Aug 2007
Malacas GT 4
Location: Talara
Operator: Empresa Electrica de Piura
Configuration: 1 X 96 MW GT11N2gas turbines
Fuel: natural gas
Operation: 1998
T/G supplier: ABB
Quick facts: The Malacas site is 1,120km north of Lima not far south of
the border with Ecuador. In 2006, EEPSA, Alstom, and ABB upgraded the GT-4
unit control system during a routine inspection outage.
Posted 19 Mar 2011



Mollendo
Location: Peru
Operator: Empresa de Generacion Arequipa SA (Egasa)
Configuration: 2 X 37.5 MW 6001E gas turbines, 3 X 10.5 MW 16MB430V engines
Fuel: diesel oil, heavy oil
Operation: 1997-1999
T/E/G supplier: Alstom, Mirrlees, Brush
EPC: Alstom
Quick facts: Construction of the IC component at Mollendo began in 1996 to
supply the Sistema Interconectado Sur Oeste (SISO) covering the
departments of Arequipa, Moquegua and Tacna. In 1997, Cuzco and Puno
departments were joined to the SISO grid. The IC plant went commercial in
Apr 1998. In 1998, the flooding of the Machupicchu hydro plant in Cuzco
led to a regional supply crisis and in Feb 1998, the government authorized
the acquisition of two GTs . These commissioned in Sep 2000. The Mollendo
plant is connected to the 138kV grid and is generally on standby since
Machupicchu went back online. The two Mollendo GTs are planned for
transfer to Independence-Pisco and conversion to Camisea natural gas at a
total cost of about $8mn.
Posted 26 Aug 2009
Termoselva
Location: Padre Abad
Operator: PIC del Peru SAC
Configuration: 2 X 78 MW GT11NM gas turbines
Fuel: natural gas
Operation: 1998
T/G supplier: Alstom
EPC: Alstom
Quick facts: This plant helps monetize Peru's large gas resource at
Aguaytia located 475km northeast of Lima. The field, with reserves of up to
440bn m³, was first discovered in 1961, but production did not begin
until mid-1998. The project owner is Aguaytia Energy, a joint venture of Duke Energy, Conduit Capital, and Maple Gas.
Posted 3 Sep 2005
Ventanilla
Location: Callao
Operator: Endesa Etevensa
Configuration: 492-MW, 2+1combined-cycle block with V84.3A1 gas turbines
Fuel: natural gas, oil
Operation: 1998-2006
HRSG supplier: ??
T/G supplier: Siemens
EPC: Siemens, Abengoa, ingendesa, Duro Felguera
Quick facts: Two oil-fired 110-MW Westinghouse W501D5 machines were
installed at Ventanilla in 1993/94. These were replaced by larger Siemens
machines in 1998. In Sep 2004, Ventanilla was switched over to natural gas from
the Camisea field. In 2006, the plant was converted to combined-cycle
operation, the first CCGT plant in Peru.
Re-posted 23 Oct 2011
