Gas Turbine and Combined-Cycle Plants in Spain - Other Regions
|
|
|
|
|
Arrubal Location: La Rioja Operator: Gas Natural SDG SA Configuration: 2 X 400 MW single-shaft combined-cycle blocks with V94.3A gas turbines Fuel: natural gas, gasoil Operation: 2004 HRSG supplier: Nooter T/G supplier: Siemens EPC: Siemens Quick facts: The project was approved in May 2003 and cost about €370mn.
Photograph courtesy of Gas Natural SDG SA |
Barranco de Tirajana Location: Islas Canarias Operator: Endesa Configuration: 2 X 210 MW, 2+1 combined-cycle blocks with 6001FA gas turbines Fuel: diesel oil Operation: 2003-2007 HRSG supplier: Babock Borsig Power T/G supplier: GE, Siemens EPC: Duro Felguera
Photograph courtesy of Hitachi Europe |
Castejon Location: Navarra Operator: HC Energia Configuration: 1 X 400 MW single-shaft combined-cycle block with GT26B gas turbine Fuel: natural gas Operation: 2003 HRSG supplier: CMI T/G supplier: Alstom EPC: Alstom, Duro Felguera Quick facts: A second block was added in 2008.
Photograph courtesy of
Alstom Power |
![]() |
![]() |
![]() |
|
Castelnou Location: Teruel Operator: Electrabel Espana SA Configuration: 800-MW, 2+1 combined-cycle with M701F3 gas turbines Fuel: natural gas Operation: 2006 HRSG supplier: CMI T/G supplier: MHI, Melco EPC: Incitec, Dragados Quick facts: Construction started on 27 Oct 2003 and commercial operations began on 5 Jul 2006. The plant cost €320mn.
Photograph courtesy of Suez |
Enercrisa Location: Burgos Operator: Enercrisa (Iberdrola) Configuration: 1 x 15 MW MF111B gas turbine CHP Fuel: natural gas Operation: 1994 T/G supplier: MHI, Tuma Quick facts: This installation supplies power and steam to the world's largest glauberite mine (sodium calcium sulfate), a mineral used in dying, solar cells, and medicine.
Photograph courtesy of Grupo Crimidesa |
Escatrón Location: Zaragoza Operator: Global 3 Energia SPCA Configuration: Two 140-MW, 2+1 CCGT blocks with LM6000P gas turbines Fuel: natural gas Operation: 2007-2008 HRSG supplier: Innovative T/G supplier: GE EPC: GE, Heymo Ingeniería Quick facts: This site comprises 40ac near the Ebro River. The plant cost about €300mn and was delayed approximately two years. Development started in Nov 2003. Photograph courtesy of Global 3 Energia SPCA |
![]() |
![]() |
|
|
Granadilla
Photograph courtesy of Endesa |
Son Reus Location: Islas Baleares Operator: Endesa Configuration: 1 x 150 MW, 2+1 combined-cycle block with 6001B gas turbines, 1 X 210 MW, 2+1 combined cycle block with 6001FA gas turbines Fuel: diesel oil Operation: 2000-2005 HRSG supplier: CMI, NEM T/G supplier: Alstom, GE, Siemens EPC: Alstom, Idom, Duro Felguera
Photograph courtesy of Hitachi Europe |
|
![]() |
||
Abbreviations: ACS = Actividades de Construccion y Servicios, BWE = Babcock & Wilcox Espanola, CC = combined-cycle, CHP = combined-heat-and-power, GE = General Electric , GT = gas turbine, HRSG = heat recovery steam generator, IPP = independent power plant, LNG = liquefied natural gas, MHI = Mitsubishi Heavy Industries, T/G = turbine generator
Data: industcards, Platts UDI World Electric Power Plants Data Base
Updated 11/08/08