CCGT Plants in Turkey - Akdeniz & Ege
Adana
Location: Adana
Operator: Enerjisa Enerji Uretim AS
Configuration: 120-MW, 2+1 CCGT with 6001B gas turbines CHP
Operation: 2001
Fuel: natural gas, naphtha, oil
HRSG supplier: SFL
T/G supplier: GE, Elin, Siemens
EPC: Siemens
Quick facts: In Mar 2001, Siemens Nederland ordered four 6001B gas turbines from GE's Essen factory for three different Enerjisa CCGT projects. The Adana power plant supplies steam and electricity to a tire plant.

Photograph courtesy of Enerjisa
Posted 2 Sep 2009

Ali Metin Kazanci
Location: Antalaya
Operator: Aksa Enerji Uretim AS
Configuration: 2 X 120-MW, 2+1 CCGT blocks with LM6000PC Sprint gas turbines, 900-MW, 2+1 CCGT with SGT5-4000F gas turbines
Operation: 2009-2010
Fuel: natural gas
HRSG supplier: Innovative Steam Technologies, NEM
T/G supplier: GE, Siemens
EPC: Aksa, BGM, Mastir
Quick facts: In Jun 2008, Ex-Im Bank announced a unique four-party $99.7mn credit agreement to support the sale of these machines, which comprise Phase-1 of the Antalya project. The export transaction met the criteria of Ex-Imís Environmental Exports Program due to the low NOx characteristics of the LM6000s. The credit agreement covers a loan from JP Morgan Chase Bank to Aksa where GE Capital Markets acted as the financial advisor. Ex-Im Bank guaranteed $55mn of the loan with the remainder guaranteed by HEXIM, Coface, and EDC. It was the first time Ex-Im Bank concluded a credit agreement involving co-financing with more than two other ECAs. Two Siemens 283-MW simple-cycle SGT5-4000F gas turbines were then ordered for Phase-2. The entire project cost about $1.1bn.

Photograph courtesy of Aksa Enerji
Re-posted 11 Dec 2013

Ataer
Location: Izmir
Operator: Ataer Enerji Elektrik Uretim AS
Configuration: 125-MW, 2+1 CCGT with LM6000PC Sprint gas turbines
Operation: 1998-2010
Fuel: natural gas
HRSG supplier: IST
T/G supplier: GE, Brush, Siemens
EPC: Stewart & Stevenson, BGM, Siemens
Quick facts: This CPP in Izmir Ataturk OSB was founded in Jul 1996. The first GT started operations in Oct 1998 on naphtha, but was switched to natural gas in Aug 2003.

Photograph courtesy of Ataer Enerji Elektrik Uretim AS
Re-posted 29 Jan 2014

Batiçim
Location: Izmir
Operator: Baticim Enerji
Configuration: 45-MW, 6+1 CCGT with Typhoon gas turbines CHP
Operation: 2003
Fuel: natural gas
HRSG supplier: ISTROENERGO GROUP as
T/G supplier: Alstom
EPC: ISTROENERGO GROUP as, B&M Engineering, ERGAZ
Quick facts: This plant was shutdown in Jan 2013 due to high gas prices and other market issues.

Photograph courtesy of ISTROENERGO GROUP as
Posted 3 Jan 2014

Cine ALES
Location: Aydin
Operator: Palmet Enerji AS
Configuration: 64-MW, 1+1 CCGT with LM6000PC-Sprint gas turbine CHP
Operation: 2012-2013
Fuel: natural gas
HRSG supplier: Aalborg
T/G supplier: GE, Thermodyn
EPC: Palmet, BGM
Quick facts: In May 2009, Palmet ordered GE equipment for this CCGT plant at Cine. The gas turbine went into operation in Dec 2012 and the steamer completed in Apr 2013.

Photograph courtesy of Palmet Enerji AS
Posted 22 Jan 2013

Denizli Enerji
Location: Denizli
Operator: RWE & Turcas Guney Elektrik Uretim AS
Configuration: 800-MW, 2+1 CCGT with SGT5-4000F gas turbines
Operation: 2013
Fuel: natural gas
HRSG supplier: NEM
T/G supplier: Siemens
EPC: Metka, Enprode, Proterm Enerji
Quick facts: This €500mn project in Kaklik is a 70:30 joint venture of RWE Holding AS and Turcas Elektrik Uretim AS. Construction began in July 2010 and commercial operation began in Aug 2013. Around 750 people were involved in plant construction. Design thermal efficiency is 56.6%.

Photograph courtesy of RWE
Re-posted 10 Dec 2013

Denizli Honaz
Location: Denizli
Operator: Acarsoy Enerji Elektrik Üretim Sanayi ve Ticaret AŞ
Configuration: 60-MW, 1+1 CCGT block with LM6000PC Sprint gas turbine
Operation: 2012
Fuel: natural gas
HRSG supplier: Innovative Steam Technologies, NEM
T/G supplier: GE, Siemens
EPC: Odaktes
Quick facts: In Jun 2011, GE announced that Acarsoy Enerji was acquiring a LM6000-PC SPRINT gas turbine for this mid-merit CCGT in Honaz district.

Photograph courtesy of Acarsoy Enerji Elektrik Üretim Sanayi ve Ticaret AŞ
Posted 15 Jan 2014

Denizli Saraykoy
Location: Denizli
Operator: AGE Enerji
Configuration: 200-MW, 2+1 CCGT with LM6000 gas turbines
Operation: 2013
Fuel: natural gas
HRSG supplier: Aalborg
T/G supplier: GE, Siemens
EPC: Enprode
Quick facts: In Sep 2008, Age Enerji was licensed to build the 200-MW Denizli Saraykoy CCGT plant in Gerali, Saraykoy district. The plant completed in Q1, 2013 at a cost of about $194mn. It is connected to the grid at 154kV.

Photograph courtesy of AGE Enerji
Posted 8 Jan 2014<

Erzin
Location: Hatay
Operator: Akenerji Elektrik Uretim AS
Configuration: 900-MW, 2+1 CCGT with 9001FB gas turbines
Operation: 2014
Fuel: natural gas
HRSG supplier: Doosan
T/G supplier: GE, Skoda
EPC: GE, Gama, Idom, Berksan Mühendislik, OOO Tri Morya
Quick facts: The Erzin CCGT plant at Iskenderun was originally developed by Egemer Elektrik Uretim AS and taken over by Akenerji in 2009. Construction started in Oct 2011. Simple-cycle operation began in Apr 2014 and the plant was declared commercial on 6 Jun 2014.

Photograph courtesy of Akenerji Elektrik
Re-posted 12 Jul 2014

Izmir
Location: Izmir
Operator: InterGen Enerji Ltd Sirketi
Configuration: 2 X 700-MW, 2+1 CCGT blocks with 9001FA+ gas turbines
Operation: 2003
Fuel: natural gas
HRSG supplier: CMI
T/G supplier: GE, Alstom
EPC: Bechtel, Enka
Quick facts: In late Oct 1997, TEAS announced that a consortium of InterGen and Enka had won the exclusive right to negotiate for 3,500-MW of CCGT capacity, one of the largest private-power development schemes in the world to that date. In Sep 2000, the partners signed $1.5bn of loan agreements for the three projects and construction started in the summer of 2000. The gas turbine purchase amounted to about $900mn, the largest order for such equipment ever in Turkey and also the largest single order for the 9FA machine to that date. GE has a 16yr gas turbine service contract.

Photograph courtesy of Enka
Re-posted 14 Aug 2010

Kemalpasa
Location: Izmir
Operator: Akenerji AS
Configuration: 130-MW, 2+1 CCGT with 6001C gas turbines
Operation: 2005
HRSG supplier: NEM
T/G supplier: GE, Elin
EPC: GE, Epro
Quick facts: This is the world's first combined-cycle based on the GE Frame 6C gas turbine. The 6C machine is 5% more efficient than the 6B turbine and the 206C block operates at 54% efficiency. GE provided all the main generating equipment plus a distributed control system.

Photograph courtesy of GE Energy
Posted 29 Dec 2005

Mersin Camis
Location: Mersin
Operator: Camis Elektrik Uretim AS
Configuration: 2 X 125-MW 9001E gas turbines CHP
Operation: 2006-2009
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE
EPC: Genel Sistem Dizayn, Eastern Lights Energy, Mastir
Quick facts: Camis Elektrik is an autoproducer providing steam and electricity to Şişecam's soda and chromium chemicals producer Soda Sanayii AS. In Mar 2012, GE was contracted to supply long-term services plus an equipment upgrade for the cogen plant.

Photograph courtesy of GE Energy
Posted 17 Mar 2012

   
Mersin Enerjisa
Location: Mersin
Operator: Enerjisa Enerji Uretim AS
Configuration: 63-MW, 1+1 CCGT with 6001B gas turbine CHP
Operation: 2003
Fuel: natural gas, naphtha, oil
HRSG supplier: SFL
T/G supplier: GE, Elin, Siemens
EPC: Siemens
Quick facts: In Mar 2001, Siemens Nederland ordered four 6001B gas turbines from GE's Essen factory for three different Enerjisa CCGT projects. The Mersin power plant supplies steam and electricity to a cement plant.

Photograph courtesy of Enerjisa
Posted 2 Sep 2009