Gas Turbine and Combined-Cycle Power Plants in Turkey -
Iç Anadolu
Ankara Bilkent
Location: Ankara
Operator: Bilkent Enerji
Configuration: 37-MW, 1+1 CCGT with RB211gas turbine, 1 X 4.8 MW Taurus 60
Operation: 1993-2003
HRSG supplier: FW
T/G supplier: Rolls-Royce, Solar
Quick facts: Rolls-Royce Power Ventures acquired a 50% share of an existing 4-MW cogeneration facility and with partner Bilkent Holding AS expanded the facility with a RB211 gas turbine, HRSG, and steam turbine installed by Foster Wheeler. Bilkent University purchases electricity and steam from the facility with the rest of the output sold to industrial companies and TEAS. RRPV sold its share to Bilkent in December 2002.

Photograph courtesy of Rolls-Royce
Posted 13 Feb 2005

Ankara Sincan
Location: Ankara
Operator: Zorlu Enerji
Configuration: 55-MW, 1+1 CCGT with LM6000 gas turbine CHP
Operation: 2003
HRSG supplier: Aalborg
T/G supplier: GE
Quick facts: This development was agreed in 2002 and the plant supplies power and steam to an Ankara industrial zone.

Photograph courtesy of Zorlu Enerji
Posted 9 Sep 2006

 

Baymina
Location: Ankara
Operator: Baymina Enerji AS
Configuration: 770-MW, 2+1 CCGT with 9001FA+ gas turbines
Operation: 2004
Fuel: natural gas
HRSG supplier: CMI
T/G supplier: GE, Alstom
EPC: VA TECH, Yuksel
Quick facts: The Baymina project was originally developed by National Power, Bayindir, and Mimag. In Sep 2001, Tractebel acquired a controlling interest in the $500mn plant. Baymina has a 15yr PPA with TETAS and a gas supply contract with Botas. The new plant connected to the main 380kV grid and is just 3km away from the main gas pipeline to Ankara.

Photograph courtesy of Baymina Enerji
Posted 24 Jun 2006

Bursa Korteks
Location: Ankara
Operator: Zorlu Enerji
Configuration: 33-MW, 1+1 CCGT with LM2500+ gas turbine, 1 X 43-MW LM6000 CHP
Operation: 1998
HRSG supplier: NEM
T/G supplier: GE, ABB
Quick facts: This plant supplies power and steam to the Zorul Korteks textile factory.

Photograph courtesy of Zorlu Enerji
Posted 9 Sep 2006

Eskisehir OSB
Location: Eskisehir
Operator: Eskisehir Sanayi Odasi
Configuration: 37-MW 6001B gas turbine CHP
Operation: 1998
HRSG supplier: B&W Espanola
T/G supplier: EGT, G-A
EPC: EPRO
Quick facts: This CHP plant supplies an industrial estate.

Photograph courtesy of EPRO
Posted 24 Aug 2008

 

Kayseri
Location: Kayseri
Operator: Zorlu Enerji
Configuration: 160-MW, 3+1 CCGT with LM6000 gas turbines CHP
Operation: 2004
HRSG supplier: Aalborg
T/G supplier: GE, Siemens
EPC: IES
Quick facts: This $97mn plant is in the Kayseri Organized Industry Zone and was built with loans from Fortis Bank and GE Capital Markets. The U.S. Export-Import Bank approved a $60mn loan guarantee to support the export of the gas turbines and Denmark's EKF reinsured $16.3mn of the financing to cover the HRSG export.

Photograph courtesy of Zorlu Enerji
Posted 9 Sep 2006

Abbreviations:  CC = combined-cycle, GE = General Electric , GT = gas turbine, HRSG = heat recovery steam generator, IES = Istraenergo, MENR = Ministry of Energy and Natural Resources, PPA = power purchase agreement, T/G = turbine generator

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 03/18/09