|
|
 |

|
|
Aswan High Dam
Location: Egypt
Operator: Hydro Plants
Electricity Production Co
Configuration: 12 X 175 MW Francis
Operation: 1967-1971
T/G supplier: LMZ, Voith, Electrosila
EPC: Hydropower Institute
Quick facts: The High Dam is up to 111m high and it is almost
1,000m long. Construction began in 1960 and one third of the total cost
(estimated to be over $1bn) was provided by the Soviet Union: 400 Soviet
engineers were used on the job. In July 2003, LMZ and Voith Siemens
Hydro were awarded a contract for the reconstruction of the 12
generators, a program expected to last six years. The €85-million
program is funded by KfW. Lake Nasser, the multipurpose reservoir behing
the dam, is about 565 km long. In areas now partially inundated were temples built by
Egyptian pharaoh Ramses II around 1200 BC. During the construction of
the High Dam, some of the temples were moved -- a unique and difficult
job -- but other monuments were submerged causing worldwide comment.
Photograph copyright by and courtesy of Ioan Triponescu
Posted 2 Jun 2004 |
Awash II & III
Location: Ethiopia
Operator: Ethiopian Electric Power Corp
Configuration: 4 X 16 MW Francis
Operation: 1966-1971
T/G supplier: Voith, Elin
Quick facts: The three Awahs plans were the first large hydro power
stations built in Ethiopia. The units at Awash II and III were
overhauled by Ingea.Photograph courtesy of
Ingea spol sro
Posted 25 Aug 2007 |
Gilgel Gibe I
Location: Ethiopia
Operator: Ethiopian Electric Power Corp
Configuration: 2 X 61.3 MW Francis
Operation: 2004
T/G supplier: Voith
EPC: Enelpower, Electroconsult, Salcost
Quick facts: This plant is near Jimma 260km
southwest of Addis on the Gilgel Gibe River. Development began in the
early 1960s and the site was selected after planning studies in the 1970s and 1980s. Construction by a consortium of
Ethiopian and North Korean firms began in 1988, but work stopped in 1994
before the dam was completed. In 1995, the government signed a new
agreement with an Italian consortium to undertake an environmental
impact assessment and complete design
and construction. Funding from the World Bank was used to complete the plant.
A 9.2km tunnel goes from the 40m dam to the powerhouse.
Photograph courtesy of Enel SpA
Posted 16 May 2004 |
 |
 |
 |
|
Jebel Aulia
Location: Sudan
Operator: National Electricity Corp
Configuration: 30.4 MW matrix turbines
Operation: 2004-2005
T/G supplier: VA TECH, Elin
EPC: VA TECH
Quick facts: The Jebel Aulia dam was built from 1933-37 for irrigation
and flood control. The site is on the White Nile 40km south of Khartoum.
The dam is 5km in length with the highest head measuring 22m. The matrix
turbine installation consists of 80 individual turbine units, divided
into 8 groups, each with 10 turbines arranged in modules of two turbines
each. Photograph courtesy of National Electricity Corp
Posted 3 Jul 2010 |
Kapichira
Location: Malawi
Operator: Electricity Supply Corp of Malawi
Configuration: 2 X 32 MW Francis
Operation: 2000
T/G supplier: Voith, Impsa
EPC: TAMS Consultants
Photograph courtesy of American
Consulting Engineers Council
Posted 25 Jul 2001
|
Khasm El Girba-2 Rebuild
Location: Sudan
Operator: National Electricity Corp
Configuration: 2 X 3.9 MW Kaplan
Operation: 1964
T/G supplier: Ansaldo
EPC: Enelpower
Photograph courtesy of Enel SpA
Posted 15 Feb 2004
|
|
 |
 |
 |
|
Kidatu
Location: Tanzania
Operator: Tanzania Electric Supply Co
Configuration: 4 X 50 MW Francis
Operation: 1975-1980
T/G supplier: Voith, Listroj, Koncar
Photograph courtesy of Koncar
Posted 17 Aug 2004 |
Lower Kihansi
Location: Tanzania
Operator: Tanzania Electric Supply Co
Configuration: 3 X 60 MW Pelton
Operation: 1999-2000
T/G supplier: Kvaerner, ABB
EPC: Norplan, Impregilo
Quick facts: This 25m dam on the Kihansi
River, a tributary to Kilombero river, impounds a small reservoir. The
dam is equipped with sediment flushing gates and an intake structure
with trash-racks and gates. The intake connects to the headrace tunnel
via a circular unlined 500m vertical headrace shaft.
Photograph courtesy of Matest
Posted 19 Mar 2006 |
Merowe
Dam
Location: Sudan
Operator: Ministry of Irrigation and Water Resource
Configuration: 10 X 125 MW Francis
Operation: 2009-2010
T/G supplier: Alstom
EPC: China International Water & Electric Corp, Sinohydro Corp, Harbin
Power Engineering Co, Jilin Province Transmission and Substation Project
Co, Lahmeyer International
Quick facts: During its implementation, this was the largest hydro construction project in
Africa and it was China’s largest overseas electricity project to date.
The scheme is at the Nile’s Fourth
Cataract and has a 60m concrete dam approximately 520m long
supported by rock- and earthfill dams on either side stretching 11km in
total. In Aug 2001, the Arab Fund for Economic and Social
Development, and other development funds in Abu Dhabi, Kuwait, Oman, and
Saudi Arabia pledged a total of €560mn to the Merowe project. The China
Import Export Bank later added €240mn with the Sudanese government
expected to make up the balance for the €1.2bn project. Resettlement was
required for up to 70,000 people affected by dam and reservoir
construction. A 400km, 500kV transmission line runs from the site to
a new 220kV substation at Khartoum. Construction started in Jun 2003.The first two units went commercial
in Mar 2009 and the last unit was commissioned by
President Omer Al-Bashir in May 2010.
Photograph courtesy of China Intl Water &
Electric Corp
Re-posted 19 Jul 2009 |
|
 |
 |
 |
|
Naga Hammadi
Location: Egypt
Operator: Hydro Plants Electricity Production Co
Configuration: 4 X 16 MW bulb
Operation: 2008
T/G supplier: VA Tech
EPC: Lahmeyer, Orascom Construction, Vinici, Bilfinger-Berger
Quick facts: The 330m long dam
at Naga Hammadi in Upper Egypt replaces a structure built between 1927
and 1930. The seven-gate dam raises up to 8m for irrigation and
hydroelectric power. The £445 project included a 1.1km canal and a 23km,
220kV line to connect to the grid.
Photograph courtesy of DSD Noell
Posted 29 Aug 2009 |
Nkula Falls-A
Location: Malawi
Operator: Electricity Supply Corp of Malawi
Configuration: 3 X 8 MW Francis
Operation: 1966-1967
T/G supplier: English Electric
EPC: Knight Piesold
Quick facts: Voith Siemens is leading a refurbishment project at the "A"
plant which will result in a slight increase in output.
Photograph courtesy of Voith
Siemens Hydro
Posted 3 Aug 2005 |
Tekeze
Location: Ethiopia
Operator: Ethiopian Electric Power Corp
Configuration: 4 X 75 MW Francis
Operation: 2009
T/G supplier: China Wanbao Engineering Co
EPC: MWH, Energoproject-Hidroinzenjering, SinoHydro, China Gezhouba
Construction, Sur Construction
Quick facts: In mid-2001, EEPCo issued a bid to build a 300-MW
power plant at the TK5 site on the Tekeze River in Tigray state 80km
west of Mekele. This project had a lengthy history as the engineering
consortium for Tis Abay-II produced feasibility studies, designs and
tender documents for a plant that turned out to be essentially on the
border with Eritrea. This location was abandoned and the project was
reborn at a different site. In Jun 2002, EEPCo awarded the EPC contract
to CWGS Joint Venture. At the time, the $224mn contract was the largest
cooperative project between China and an African country. The main
structure is a 185m, double-curvature concrete dam which id now the
tallest in Africa. Over 3,500 workers were involved in plant
construction, of which 750 were expats from four countries. Power
generation started in Aug 2009 despite the fact that the reservoir was
not completely filled.Photograph courtesy of Ethiopian Electric Power Corp
Posted 18 Nov 2009 |
|
|
 |
|
|
|
Turkwel
Location: Kenya
Operator: Kenya Electricity Generating Co Ltd
Configuration: 2 X 54 MW Francis
Operation: 1991
T/G supplier: Neyrpic, Alsthom-Jeumont
EPC: Sogreah, Spie-Batignolles
Quick facts: This project was a major engineering
accomplishment and includes a thin, double-cambered arch dam with a
maximum height of 150m, a 5.5km headrace and penstock, and an underground
powerhouse 250m deep. The project was built in six years and cost
Ksh7.5bn, substantially more than originally estimated.
Photograph courtesy of Kenya Electricity Generating Co Ltd
Posted 25 Jul 2007 |
|