Hydroelectric Plants in Belarus

Chigirin
Location: Mogilev
Operator: Mogilevenergo
Configuration: 3 X 550 kW
Operation: 1959
T/G supplier: ??
EPC: Spetsgidroenergomontazh
Quick facts: This SHP is on the River Drut. Development took about 3yrs. The plant is planned for reconstruction.

Photograph courtesy of Belarusian HPP (wikipedia)
Posted 2 Apr 2010

Kobrin
Location: Brest
Operator: RUESP Dnieper-Bug Waterway
Configuration: 3 X 100 kW
Operation: 2009
T/G supplier: ??
EPC: AEnergy
Quick facts: This SHP is on a segment of hte 547km Dnieper-Bug Waterway. The system including locks and other facilites is owned by the Ministry of Transport and Communications.

Photograph courtesy of AEnergy
Posted 26 Apr 2014

Nemnovskaya
Location: Grodno
Operator: Grodnoenergo
Configuration: 5 X 3.6 MW pit
Operation: 2012
T/G supplier: Mavel, TES
EPC: Marvestan Group
Quick facts: In Jul 2009, Mavel signed a contract to provide electromechanical equipment for this greenfield, low-head SHP on the Neman River 8km from Grodno City. Financing was provided by the Czech Export Bank. Each 3m diameter turbine utilizes the head of 7 meters and flow of 60 cms. The project was the first for Mavel in Belarus and the first utilizing CEB financing.

Photograph courtesy of Mavel sro
Posted 17 Apr 2013

Osipovichi
Location: Mogilev
Operator: Mogilevenergo
Configuration: 3 X 725 kW
Operation: 1953
T/G supplier: ??
Quick facts: This is the largest installed hydroelectric plant in Belarus. Construction began in 1946 at an old watermill site on the River Svisloch. The plant was put online in Nov 1953. Normal waterflow is only sufficient for two sets. The plant is under reconstruction.

Photograph courtesy of Belarusian HPP (wikipedia)
Posted 2 Apr 2010

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 03-Feb-2016