Apolônio Sales (Moxotó)
Location: AL
Operator: Cia Hidroeletrica do Sao Francisco
Configuration: 4 X 100 MW Kaplan
Operation: 1977
T/G supplier: Dominion Engineering, BBC
EPC: Sofrelec, Mendes Junior
Quick facts: This plant is part of the Paulo Alfonso complex on the Rio São Francisco.
The dam is 30m high and the total length of the dams and abutments is
2,825m.
Photograph courtesy of Cia Hidroeletrica do Sao Francisco
Posted 5 May 2007 |
|
Xingo
Location: AL
Operator: Cia Hidroeletrica do Sao Francisco
Configuration: 6 X 527 MW Francis
Operation: 1995-1997
T/G supplier: Voith, Siemens
EPC: Promon, Cia Brasileira de Projetos e Obras, Mendes Junior, Constran SA
Quick facts: In Jan 1995, the first of six 500-MW units went online at
the Xingo hydroelectric plant bout 60km downstream from the Paulo
Alfonso complex on the Rio São Francisco at the border of Alagoas and
Sergipe. Initial studies on the site began during the 1950s, but the
first construction contracts were awarded until Dec 1982. Work on
the 850m long, 140m high dam began 5yrs later, but continued for only
18mos when the global debt crisis caused disbursements of the $650mn
syndicated loan to stop. About 18mos later, construction work resumed
and in Jul 1994, the Xingo Reservoir was filled. The sixth unit
commissioned in Sep 1997. Xingo cost about $610/kW. The dam is 140m high and 830m long.
Photograph courtesy of Cia Hidroeletrica do Sao Francisco
Posted 5 May 2007 |