Hydroelectric Plants in Brazil - other states

Alto Sucuriu
Location: MS
Operator: Silea Participacoes Ltda
Configuration: 2 X 14.5-MW Kaplan
Operation: 2008
T/G supplier: Andritz
EPC: DM Construtora de Obras Ltda
Quick facts: This project was authorized by ANEEL in Dec 2002 and went into operation in Aug 2008. The site is on the Rio Sucuriu in the municipalities of Agua Clara, Chapadao do Sul, and Costa Rica. The development company is Onix Geracao de Energia SA.

Photograph courtesy of Silea Participacoes Ltda
Posted 22 Dec 2012

Balbina
Location: AM
Operator: Eletronorte
Configuration: 5 X 50-MW Kaplan
Operation: 1989-1990
T/G supplier: Neyrpic, Mecanica de la Pena, GE

Photograph courtesy of Eletronorte
Posted 30 May 2002

Belo Monte
Location: PA
Operator: Norte Energia SA
Configuration: 18 X 611-MW Francis
Operation: 2016-2019
T/G supplier: Consorcio ELM (Alstom, Andritz and Voth)
EPC: Camargo Correa, Odebrecht, OAS, Queiroz Galvao, Contern, Galvao Engenharia,Serveng-Civilsan, J Malucelli Cetenco
Quick facts: Development of this megaproject on the Rio Xingu in Altamira started in 1975. In Nov 1998, Eletrobras re-started planning work. In Feb 2000, Eletrobras said that it expected that the plant would be built by the private sector on a concession basis. Licensing was stalled in Jun 2009 when local authorities won an injunction against the project alleging deficiencies in the EIA. This injunction was lifted by a federal court in Aug 2009 and the scheme weathered many more legal challenges. In Apr 2010, the 35yr concession went to Norte Energia. The lead owners are Eletronorte (19.98%), Eletrobras (15%), and CHESF (15%), with 8 other companies and entitites holding stakes. The spillway has a total length of 445.5m and has 18 radial gates, each 20m long and 22m high. The first machine began testing on 17 Feb 2016.

Photograph by Norte Energia SA
Posted 27 Feb 2016

Bonfante
Location: RJ
Operator: Brasil PCH SA
Configuration: 1 X 19 MW
Operation: 2008
T/G supplier: Alstom
EPC: Engevix, Seta Engenharia
Quick facts: The Bonfante project was authorized by Aneel in 2001 and is located near Levy Gasparian on the Rio Paraibuna. The plant cost R$90.9mn. Brasil PCH is a special purpose company owned by Petrobras, Araguaia Centrais Elétricas SA, BSB Energética SA, Eletroriver SA and Jobelpa SA.

Photograph courtesy of Seta Engenharia
Posted 16 Aug 2009

Costa Rica
Location: MS
Operator: Costa Rica Energética
Configuration: 3 X 5.3- MW Kaplan
Operation: 1999
T/G supplier: Alstom, Toshiba
EPC: DM Construtora de Obras Ltda
Quick facts: This project in Mar 1999. The site is on the Rio Sucuriú in Costa Rica municipality. The development company is a JV of EDP company Energest (51%) and Silea (49%).

Photograph courtesy of Silea Participacoes Ltda
Posted 23 Dec 2012

Curemas
Location: PB
Operator: Cia Hidroeletrica do Sao Francisco
Configuration: 2 X 1.76-MW Francis
Operation: 1957-1959
T/G supplier: Voith, Westinghouse, Siemens
EPC: DNOCS
Quick facts: Curemas uses water stored by two dams on the Rio Pianco and a third on the Rio Aguiar linked by a canal. The powerhouse is below a 2,670m dam.

Photograph courtesy of Cia Hidroeletrica do Sao Francisco
Posted 6 May 2007

Ferreira Gomes
Location: AP
Operator: Alupar Investimento SA
Configuration: 3 X 84 MW Kaplan
Operation: 2014-2015
T/G supplier: Voith
EPC: Voith, Alusa
Quick facts: In May 2007, Eletronorte issued a call for partners for the Ferreira Gomes and Cachoeira do Caldeirao HPPs on the Rio Araguari. The R$810mn project was approved in Jul 2010 for the A-5 energy auctionand the 35yr concession assigned to Alupar in Sep 2010. Plant testing began in Aug 2014 and the first unit went commercial on 30 Dec 2014. Unit-3 went commercial on 30 Apr 2015.

Photograph courtesy of Ministerio do Planejamento
Posted 20 Mar 2016

Humaitá
Location: PE
Operator: Grupo Farias - Vale Verde
Configuration: 1 MW
Operation: 1925
T/G supplier: ??
Quick facts: This photo of a sugar factory small hydro was taken in 1940. The Pedroza mill is one of the oldest in the state still in full operation.

Photograph by Hart Preston (Life archive on Google)
Posted 7 Mar 2009

Jirau
Location: RO
Operator: Energia Sustentável do Brasil SA
Configuration: 50 X 75-MW bulb
Operation: 2013-2016
T/G supplier: Alstom, Voith, Andritz, Dongfang
EPC: Tractebel Engineering, Camargo Correa
Quick facts: In Feb 2006, ANEEL published technical feasibility studies and economic and environmental impact studies for UHE Jirau and UHE Santo Antônio on the Rio Madeira near Porto Velho, RO. ESBR is invested by GDF Suez (40%), Eletrosul (20%), Chesf (20%) and Mizha Participações SA (20%). The winning auction price was R$71.37/MWh. The HPP was licensed for construction on 3 Jun 2009. In 2011, expansion from 44 to 50 units was approved and construction began on three 500kV lines to the Porto Velho S/S and grid connection. The main dam is a 1,130m long, 62m tall rockfill structrure with asphalt core. There are two powerhouses, one on the right bank with 28 sets and one on the left bank with 22 sets.The first unit went commercial on 6 Sep 2013.

Photograph courtesy of Ministerio do Planejamento
Re-posted 20 Mar 2016

Luiz Gonzaga
Location: PI
Operator: Cia Hidroeletrica do Sao Francisco
Configuration: 6 X 247-MW Francis
Operation: 1988-1990
T/G supplier: Riva, Coemsa, Ansaldo, Voith, Siemens
EPC: Hidroservice, Mendes Junior
Quick facts: The dam and abutments measure 4,700m in length and reach 105m in height.

Photograph courtesy of Cia Hidroeletrica do Sao Francisco
Posted 6 May 2007

Mascarenhas
Location: ES
Operator: EDP Escelsa
Configuration: 3 X 43-MW Kaplan, 1 X 51 MW
Operation: 1974-2006
T/G supplier: AC, GE, GE Hydro Inepar
EPC: Leme Engenharia
Quick facts: Plant development was started by Cia Central Brasileira de Força Elétrica (later Eletrobrás). When the new power station went into operation at 123 MW, it fulfilled the state's electricity requirement for a time. In 2000, the plant was upgraded to its present capacity by GE Hydro Inepar, and a 51-MW fourth unit was added later. The plant is connected to the grid at 230kV.

Photograph courtesy of EDP Energias do Brasil
Re-posted 24 Apr 2013

Monte Serrat
Location: RJ
Operator: Brasil PCH SA
Configuration: 2 X 12.- MW Kaplan
Operation: 2009
T/G supplier: Alstom
EPC: Engevix, Seta Engenharia
Quick facts: This plan is sited between the municipalities of Simão Pereira, MG, and Comendador Levy Gasparian, RJ. BNDES financed R$80.9mn for the project, or 74% of the total investment, R$109.7mn.

Photograph by Seta Engenharia
Posted 16 Aug 2009

Paraiso
Location: MS
Operator: Enersul
Configuration: 3 X 10.8-MW Francis
Operation: 2003
T/G supplier: Voith Siemens

Photograph courtesy of Voith Siemens Hydro
Posted 23 Sep 2003

Pimentel
Location: PA
Operator: Norte Energia SA
Configuration: 6 X 39 MW
Operation: 2016-2017
T/G supplier: Andritz
EPC: Camargo Correa, Odebrecht, OAS, Queiroz Galvao, Contern, Galvao Engenharia,Serveng-Civilsan, J Malucelli Cetenco
Quick facts: Pimentel is part of the Belo Monte HPP complex. It is an upstream barrage and hydro plant with a reservoir and two 12km canals running to the main plant reservoir.

Photograph by Norte Energia SA
Posted 27 Feb 2016

Ponte Alta
Location: RS
Operator: Brookfield Energia Renovavel
Configuration: 2 X 6.71-MW Francis
Operation: 2007
T/G supplier: Hacker

Photograph courtesy of Hacker Industrial Ltda
Posted 30 Aug 2009

Santa Fe
Location: RJ
Operator: Brasil PCH SA
Configuration: 2 X 15 MW
Operation: 2008
T/G supplier: Alstom
EPC: Koblitz
Quick facts: The Santa Fe project was authorized by Aneel in 2002 and is located near Levy Gasparian on the Rio Paraibuna. The plant cost R$141.3mn and went commercial on 9 May 2008.

Photograph by Sichan (Panoramio)
Posted 16 Aug 2009

Santo Antonio
Location: RO
Operator: Santo Antônio Energia
Configuration: 50 X 72-MW bulb
Operation: 2012-2016
T/G supplier: Alstom, Bardella, Andritz
EPC: Odebrecht, Andrade Gutierrez
Quick facts: In Feb 2006, ANEEL published technical feasibility studies and economic and environmental impact studies for UHE Jirau and UHE Santo Antônio on the Rio Madeira near Porto Velho, RO. These are unique installations with dozens of very large bulb turbines. In Dec 2007, the Madeira Energia consortium of Furnas and Odebrecht won the concession for Santo Antônio. The bid was R$78.87/kWh as compared to R$122/kWh, the maxium bid set by ANEEL. In Sep 2008, Alstom Hydro won a contract worth approximately €500mn from Madeira Energia for 19 turbines and 22 generators. In Dec 2008, Andritz won a €250mn award for 12 T/G sets and 24 governors. The plant has 15 gates forming the main spillway. The first eight units went online in 2012 and 32 were in operation by the end of 2014

Photograph courtesy of Santo Antonio Energia
Re-posted 14 Feb 2015

Santo Antonio do Jari
Location: AP
Operator: EDP Energias do Brasil SA
Configuration: 3 X 124.5 MW, 1 X 3.4 MW Kaplan
Operation: 2014-2015
T/G supplier: Alstom
EPC: CESBE, Areva Kobiltz, Alstom
Quick facts: This UHE is on the Rio Jari on the border of Amapa and Para. It was developed by Consorcio Amapa Energia, a company controlled by Participa Empreendimentos Imobiliarios e Participacoes Ltda. It has a 1,300m dam and a 1,200m long spillway section. A 20km, 230kV tie-line connects to the Laranjal do Jari S/S. Majority ownership was acquired by EDP in Jun 2011 when the final environmental license was issued, and the main units were connected from Aug to Dec 2014, about 4mos ahead of schedule.

Photograph courtesy of EDP
Posted 22 May 2016

   
  Sao Simao
Location: ES
Operator: Brasil PCH SA
Configuration: 2 X 13.5-MW Francis
Operation: 2009
T/G supplier: Alstom
Quick facts: This R$ 104.4mn project is on the Rio Itapemirim near Alegre. It went commercial on 17 Feb 2009.

Photograph courtesy of Petrobras
Posted 28 Dec 2011

 

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 22-May-2016