|
Balambano
Location: South Sulawesi
Operator: PT Inco
Configuration: 2 X 70 MW Francis
Operation: 1999-2000
T/G supplier: CGE
EPC: SNC, Astaldi, Fluor, Thiess Contractors
Quick facts: Balambao is donwsream of the Larona power station and both
plants are used to supply for the Inco nickel smelter at Saroako. The
90m RCC dam has a crest length of 350m. The remote site on the Larona
River is 30km from the nearest population center. Work on contract
procurement began in Apr 1995. Unit-1 was placed
into service on 31 Oct and Unit-2 followed on 28 Nov 1999.
Photograph courtesy of
Astaldi SpA
Posted 26 Feb 2006 |
Cirata
Location: West Java
Operator: PT Pembangkitan Jawa Bali
Configuration: 8 X 126 MW Francis
Operation: 1988-1998
T/G supplier: Voest, Elin
EPC: Coyne, Sinotech,Taisei
Quick facts: When Phase II was completed in 1998, this became
Indonesia's largest hydroelectric plant.
Photograph courtesy of Taisei Corp
Posted 15 Sep 2004 |
Kotapanjang
Location: Riau
Operator: PT PLN
Configuration: 3 X 38 MW Kaplan
Operation: 1998
T/G supplier: Boving, Elin
EPC: Hazama
Quick facts: Output from the plant supplies about 20% of the electric power in the provinces of West Sumatra and Riau
which between them have a population of over 9mn. JBIC supported the plant
and associated transmission line project.
Photograph copyright by and courtesy of
VA TECH
Posted 22 Sep 2005 |
|
Larona
Location: South Sulawesi
Operator: PT Inco
Configuration: 3 X 65 MW Francis
Operation: 1977
T/G supplier: Sulzer, Hitachi, GE, VA TECH
EPC: Knight Piesold, PT Vale Inco
Quick facts: This was the original power source for the PT Inco
smelter at Saroako. The design features a 7km intake canal, two radial
intake control gates, a head pond, and three 1.3km penstocks equipped with
bypass valves to protect the penstocks during load rejections. From
2003-2006, the PT Inco staff and its contractors development and
implemented a comprehensive plant controls upgrade on Larona-3. The actual
installation took 12 days. In 2007, VA TECH was contracted to supply generator
upgrades and other services for Larona.
Photograph courtesy of
Andritz
Re-posted 14 Jan 2010 |
Musi
Location: South Sumatra
Operator: PT PLN
Configuration: 3 X 70 MW
Operation: 2006
T/G supplier: VA TECH
EPC: PT Indra Karya, Shimizu Corp, Nippon Koei Co
Quick facts: At completion, this was the country’s largest hydro
plant outside Java. The project was built with ADB funding. It was placed in postponed status in Sep 1997 and development resumed in May 2000.
The scheme includes a 213km, 150kV transmission line from the plant to Curup substation and on to Bukit Asam substation. Annual output is expected to be about 470 GWh.
Photograph courtesy of
Nielsen-Wurster Group
Posted 23 Oct 2005 |
Saguling
Location: West Java
Operator: PT Indonesia Power
Configuration: 4 X 178-MW Francis
Operation: 1986-1987
T/G supplier: Toshiba, Mitsubishi Electric
EPC: SABCON, Newjec Inc,
Proyek Induk Pembangkit Hidro
Quick facts: Saguling is a rockfill dam nearly 100m high and over
300 m long. It inundated about 5,600ha in a densely populated region and
there has been considerable study of the ecological and socioeconomic effects of dam
construction. The site is 40km
from Bandung city and was built on the Citarum River, the largest river in
West Java. Originally, Saguling was planned for power production only but the reserovir
was repurposed to support fisheries, aquaculture, tourism, and water
supply. The plant could be extended to 1,400 MW in the future.
Photograph courtesy of
Newjec Inc
Posted 12 Jul 2008 |
|
|
Sudirman (Mrica)
Location: Central Java
Operator: PT Indonesia Power
Configuration: 3 X 61.5-MW Francis
Operation: 1988-1989
T/G supplier: ASEA, Kvaerner
EPC: SABCON
Quick facts: This multipurpose scheme has a
800m long, 110m tall earth-filled and rock main dam across the Serayu
River. Other high-level dams stretch out on either side of the
main dam to give a total crest length of more than 5km. The open-air power
house is connected to the reservoir by a 570m pressure tunnel. The first
study for Mrica was commissioned in 1970, but work did not get
underway until Dec 1982. After 6mos, construction had to be halted
until Mar 1984 for financial reasons. The main project dates were
originally set back two years, but it took less time than expected to
restart; at the end of the contract, only about a year was lost and the final
turbine was commissioned 2mos ahead of schedule.
Photograph courtesy of Kvaerner
Posted 6 Apr 2004 |
|