|
 |
 |
 |
|
Alto Mallero
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 1 X 1.13 MW, 1 X 3 MW, 1 X 410 kW, 1 X 600 kw Pelton/Francis
Operation: 2001
T/G supplier: Bouvier, Tamanini
Quick facts: This plant is in Valmalenco Chiareggio.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
Angelo Bertini Rebuild
Location: MI
Operator: Edison SpA
Configuration: 4 X 3.16 MW Francis
Operation: 2002
T/G supplier: VA TECH
Quick facts: Bertini was constructed between 1895 and 1898 in Paderno
d'Adda and named for Angelo Bertini, who supervised the project and was also general manager of Societe Edison
between 1891 and 1915. At completion, it was one of the largest power stations in Europe and
its 32km, 13.5kV transmission tie-line was a world record.
The original equipment at the Bertiini plant consisted of seven 1.5-MW sets. Paolo Milani and Guido Semenza
were the lead hydraulic and electrical engineers, respectively. The
turbines were supplied by Milan's Riva & Monneret, who had just built
turbines for the Niagara project, and the generators were sourced from
Brown Boveri with transformers from Ganz and switches from General
Electric.
Photograph courtesy of
Edison SpA
Posted 27 Feb 2010 |
Armisa
Location: SO
Operator: Edison SpA
Configuration: 2 X 7.29 MW Pelton/Francis
Operation: 1929
T/G supplier: ??
Quick facts: This plant has two generators, each driven by a Pelton
turbine and a Francis turbine. It was rebuilt in 1997/98.
Photograph courtesy of
Edison SpA
Posted 18 Feb 2008 |
 |
 |
 |
Biraghetta
Location: PV
Operator: ERG Renew
Configuration: 2 X 241 kW S-Turbine
Operation: 1936
T/G supplier: Sulzer Escher Wyss
Qucik facts: ERG's hydro plants are along irrigation canals of
Associazione Irrigazione Est Sesia. This
plant is in Cilavegna.
Photograph courtesy of ERG Renew
Posted 27 Jun 2010
|
Bisolo
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 2 X 5 MW Pelton
Operation: 2006
T/G supplier: Bouvier
Quick facts: This plant is in Valmasino.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
Bocco
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 1 X 2.3 MW Pelton
Operation: ??
T/G supplier: Bouvier
Quick facts: This plant is in Andevenno.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
 |
 |
 |
Cassolnovo
Location: PV
Operator: ERG Renew
Configuration: 510 kW
Operation: ??
T/G supplier: ??
Photograph courtesy of ERG Renew
Posted 27 Jun 2010
|
Champagne I&II
Location: AO
Operator: CVA SpA
Configuration: 3 X 3.8 MW, 2 X 13.5 MW Pelton
Operation: 1921-1938
T/G supplier: ??
Quick facts: The Champagne I building is a fine example of industrial
architecture dating to the Belle Epoque era. The site is open for tours
and the interior features many attractive fittings and wall treatments.
Photograph courtesy of Regione Autonoma Valle d'Aosta
Posted 7 Jun 2009 |
Confienza
Location: PV
Operator: ERG Renew
Configuration: 228 kW
Operation: ??
T/G supplier: ??
Photograph courtesy of ERG Renew
Posted 27 Jun 2010
|
 |
 |
 |
|
Entovasco
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 1 X 1.36 MW Pelton
Operation: 2002
T/G supplier: Bouvier
Quick facts: This plant is in Senevedo.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
Gressoney
Location: AO
Operator: CVA SpA
Configuration: 2 X 5.5 MW
Operation: 1921
T/G supplier: ??
Photograph courtesy of
GSE SpA
Posted 25 May 2009 |
Guido Semenza-I
Location: BG
Operator: Edison SpA
Configuration: 2 X 3.4 MW Kaplan
Operation: 1920
T/G supplier: Riva, TIBB
Quick facts: This is a plant of historical importance on the left bank
of the Adda River near the Robbiate Dam. Construction began in 1917. The plant designer was Paolo Milani and the electric work was done by
Guido Semenza. The project manager was Angelo Bertini, technical director
at Edison. The plant was rebuilt in 2001
Photograph by Frieda (wikipedia)
Posted 24 Oct 2010 |
 |
 |
 |
|
Grosotto
Location: SO
Operator: A2A SpA
Configuration: 1 X 10 MW Pelton
Operation: 1910
T/G supplier: ??
Quick facts: Grosotto ran with three 10-MW sets until a major flood in
July 1987 put the facility and its sister plant Boscaccia out of service.
A new 10-MW T/G set was commissioned in Oct 2004.
Photograph courtesy of A2A SpA
Posted 8 Aug 2009 |
Grosio
Location: SO
Operator: A2A SpA
Configuration: 3 X 107 MW Pelton, 1 X 110 MW Francis
Operation: 1960-2002
T/G supplier: Ansaldo, Voith, ABB
Quick facts: Construction at Grosio started in 1956 and the first two
units came online 4yrs later. Water for the plant is secured from about 8
different streams and waterways using the Valgrossina Dam. A fourth unit
was in the original design, but not completed for about 40yrs. At that
time, the rotors of the three existing sets were also replaced and various
upgrades were made to the plant electrical systems.
Photograph courtesy of A2A SpA
Posted 8 Aug 2009 |
Langosco
Location: PV
Operator: ERG Renew
Configuration: 450 kW
Operation: ??
T/G supplier: ??
Photograph courtesy of ERG Renew
Posted 27 Jun 2010
|
 |
 |
 |
|
Lovero
Location: SO
Operator: A2A SpA
Configuration: 2 X 24.5 MW Francis
Operation: 1948
T/G supplier: ??
Quick facts: Lovero is downstream from Grosio and also uses water from
the Grosotto complex. One new runner has been installed and some new
collection basins were installed to improve water flows.
Photograph courtesy of A2A SpA
Posted 8 Aug 2009 |
Maen Rebuild
Location: AO
Operator: CVA SpA
Configuration: 3 X 8 MW Pelton
Operation: 2002
T/G supplier: Sulzer
Quick facts: Maen was built in the 1920s and uses
water from the Cignana and Perreres reservoirs.
Photograph courtesy of Enel SpA
Posted 5 Sep 2004 |
Nuova Canale Viola
Location: SO
Operator: A2A SpA
Configuration: 1 X 400 kW Kaplan
Operation: 2006
T/G supplier: ??
Quick facts: This new minihydro unit was built to exploit the head
between the Nuovo Canala Viola and Cancano Reservoir. It is located near
the Bormio ski resort at the top of the Valtellina valley formed by
the Adda River.
Photograph courtesy of A2A SpA
Posted 8 Aug 2009 |
 |
 |
 |
|
Nuvolento
Location: BS
Operator: Consorzio di Bonifica Medio Chiese
Configuration: 1 X 540 kW Kaplan
Operation: 2010
T/G supplier: Serman
EPC: F.lli Baruzzi Srl
Quick facts: This SHP plant is on the Naviglio di Brescia, part of the
canal system associated with the Chiese River.
Photograph courtesy of F.lli Baruzzi Srl
Posted 16 Jan 2011 |
Poschiavino
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 1 X 1.28 MW Axial
Operation: 2009
T/G supplier: Andritz
Quick facts: This plant is in Villa di Tirano.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
Premadio
Location: SO
Operator: A2A SpA
Configuration: 2 X 74 MW, 1 X 78 MW Pelton
Operation: 1956-2003
T/G supplier: Riva, VA Tech, Ansaldo
Quick facts: The Premadio power station uses about 33km of tunnels and
waterways basically originating from the Cancanao and S Giacomo
reservoirs. A third machine was added in Dec 2003.
Photograph courtesy of A2A SpA
Posted 8 Aug 2009 |
 |
 |
 |
|
Prevalle Chiese
Location: BS
Operator: A2A SpA
Configuration: 2 X 900 kW, 1 X 740 kW Francis
Operation: 1922
T/G supplier: Riva, DePretto Escher Wyss, Marelli
Quick facts: The intake for this SHP is in Comune di Muscolina and water
travels from the Chiese 3.4km to the powerhouse. Two overhead connections
originate at the plant, one to Naviglio PS and the second towards Brescia.
Annual output is about 9 GWh.
Photograph courtesy of A2A SpA
Posted 17 Jan 2011 |
Scerscen
Location: SO
Operator: Tozzi Renewable Energy SpA
Configuration: 2 X 2.5 MW Pelton
Operation: 2002
T/G supplier: Bouvier
Quick facts: This plant is in Lanzada.
Photograph courtesy of Tozzi
Renewable Energy SpA
Posted 15 Feb 2010 |
Trezzo d'Adda
Location: MI
Operator: Enel
Configuration: 6 X 2 MW Kaplan
Operation: 1999
T/G supplier: ??
Quick facts: Trezzo d'Adda was
originally constructed in 1906 and rebuilt from 1997-1999. The plant is
also called Taccani. It was originally commissioned from architect Gaetano Moretti and hydraulic engineer
Adolfo Covi by the textile factory owner Cristoforo Benigno Crespi.
Photograph courtesy of
Enel SpA
Posted 30 Oct 2004 |
|
|
 |
|
|
|
Verres
Location: AO
Operator: Compagnia Valdostana Delle Acque SpA
Configuration: 2 X 3 MVA, 1 X 2.15 MVA, 1 X 2.5 MVA Pelton
Operation: 1911
T/G supplier: ??
Quick facts: Verres is part of the Dora Baltea canal system and was
originally built in 1911. The machinery was reconstructed in 1994-1999.
A 2.8km canal leads to a 1.4m penstock. The horizontal Pelton turbines
generate about 50,000 MWh/yr.
Photograph courtesy of
GSE SpA
Posted 25 May 2009 |
|
|
 |