|
Bureyskaya
Location: Amur - Far Eastern
Operator: RusHydro
Configuration: 6 X 335 MW Francis
Operation: 2003-2008
T/G supplier: LMZ, Electrosila
EPC: Lenhydroproject, Bureyagesstroy
Quick facts: This multiuse project is a lead
development scheme for Russia’s Far East. It is designed to reduce
regional fossil fuel consumption, allow for power exports to China, and
reduce flooding on the Bureya and Amur rivers. Bureyskaya HPS was approved
in 1982 and construction began the following year. The first unit was put
online in Jul 2003 by President Vladimir Putin and senior representatives
from RAO UES. The concrete gravity dam is 719m long and 140m high. A
unique design feature is the fact that all the main assembly and testing
on the electromechanical equipment has been done at the remote site. The
hydrogenerators are the largest air cooled machines in Russia and the CIS
countries.
Photograph
courtesy of Lenhydroproject
Posted 3 Jul 2006 |
Cheboksarskaya
Location: Chuvash Republic - Volga
Operator: RusHydro
Configuration: 18 X 78 MW Kaplan
Operation: 1980-1985
T/G supplier: Tyazhmash, Electrosila
EPC:
HPI Kuibyshev,
Cheboksargesstroy
Quick facts:
Development at the
Cheboksarskaya site dates to 1931 when it was one of 10 proposed hydro
plants on the Volga River (9 were built). In the 1950s, HPI worked
on the original design and this was modified beginning in 1960.
Originally, 32 bulb turbines were specified but this was changed to 18
vertical Kaplan units with several important design innovations.
Construction began on 22 Jan 1967 and the first unit went commercial on 31
Dec 1980.
Cheboksarskaya has 4.5km of associated structural waterworks
including a 980m earthen dam reaching 42m height plus a a 548.5m
powerhouse. For 30yrs, the plant has operated with reservoir elevation of
around 63m as opposed to the design elevation of 68m. The required works
were authorized in Apr 2010 and are expected to complete in 2012. In May
2008, HydroGK began electromechanical upgrades at Cheboksarskaya and to
date two machines have been rebuilt. The PS is connected to the grid two
220kV circuits and three 500kV circuits.
Photograph
courtesy of RusHydro
Posted 2 Feb 2011 |
Kolyma
Location: Magadan - Far Eastern
Operator: Magadanenergo
Configuration: 5 X 108 MW
Operation: 1981-1996
T/G supplier: LMZ, Elsib
EPC: Lenhydroproject
Quick facts: In 1999, a 710km line from Magadan
to Ust-Omchug was completed allowing power from the Kolyma to
replace output from the Magadan CHP plant. Another large customer for the
plant output is the Omchak gold mine.
Photograph courtesy of JSC SibCOTES
Posted 6 Jan 2007 |
|
Nizhnekamsk
Location: Tatarstan Republic - Volga
Operator: Tatenergo
Configuration: 16 X 75 MW Kaplan
Operation: 1979-1987
T/G supplier: LMZ, Elsib Photograph
courtesy of Tatenergo
Posted 10 Sep 2006 |
Vilyusk
Location: Sakha Republic - Far Eastern
Operator: Alrosa Company Ltd
Configuration: 4 X 77 MW Kaplan, 4 X 85 MW Kaplan
Operation: 1968-1978
T/G supplier: Kharkov, Elsib
EPC: Lenhydroproject
Quick facts:
This is the largest hydroelectric complex in the Yakutia region and is
used to power Alrosa diamond mining operations and also supplies the local
grid.
Photograph
courtesy of RAO UES
Posted 8 Jul 2007
|
Zeya
Location: Amur - Far Eastern
Operator: RusHydro
Configuration: 4 X 225 MW, 2 X 215 MW Deriaz
Operation: 1975-1980
T/G supplier: LMZ, Electrosila
EPC: Lenhydroproject, Bureyagesstroy
Quick facts:
This was the first large-scale hydro station in Pacific Russia and is an
area with annual temperature ranges of up to 80C. The plant has
adjustable-blade diagonal-flow turbines that were the largest in the world
at completion. This design allows for operation at low water storage
levels. The 714m long, 98m high hollow concrete buttress dam uses
cavitation-durable concrete with coarse-gravel filling, also a first. Part
of HydroWGC.
Photograph
courtesy of Zeya GES
Posted 21 May 2005 |