Hydroelectric Power Plants in Turkey - Dogu Anadolu

Keban
Location: Elazig
Operator: EUAS
Configuration: 4 X 157.5 MW, 4 X 175 MW Francis
Operation: 1974-1982
T/G supplier: Voest, Neyrpic, AEG
EPC: Ebasco, Sogea
Quick facts: The Keban Dam was the first of the large dams to be built on the Euphrates River. It created a reservoir extending 50km upriver and 100km upriver in the Murat River valley to the east. The Murat joins the Euphrates about 7km north of the dam.

Photograph by Onur Onur (TrekEarth)
Posted 25 Feb 2007

Ozluce
Location: Elazig
Operator: EUAS
Configuration: 2 X 100 MW Francis
Operation: 1998-1999
T/G supplier: Kvaerner, AEG
EPC: Temelsu, Ozlatin
Quick facts: President Suleyman Demirel opened the project in Dec 1999 after 14yrs of construction. The facility has a 144m rockfill dam and cost 273tn lira.

Photograph courtesy of Türkiye Müteahhitler Birligi
Posted 10 Dec 2006

Ozluce Izpir
Location: Erzurum
Operator: Aksu Enerji ve Ticaret AS
Configuration: 2 X 18.2 MW
Operation: 2013
T/G supplier: Hangzhou Yatai
EPC: Aksu, Enerden
Quick facts: This project in Izpir district started construction in Jul 2011 and completed at the end of 2013.

Photograph courtesy of Aksu Group
Posted 29 Dec 2014

Pinar
Location: Elazig
Operator: AGE Insaat ve Ticaret AS
Configuration: 3 X 10 MW Francis
Operation: 2009
T/G supplier: Hangzhou Yatai
EPC: Age Insaat, Dogru Muhendislik, Eltes Enerji Mühendislik
Quick facts: This project is in Tut District on the Goksu River.

Photograph courtesy of AGE Insaat ve Ticaret AS
Posted 11 Apr 2011

Seyrantepe
Location: Elazig
Operator: Bilgin Enerji
Configuration: 2 X 25.7 MW Francis
Operation: 2008
T/G supplier: Alstom
EPC: Su-Yapi, Limak
Quick facts: The Seyrantepe project is on the Peri River and is a partnership between Bilgin Elektrik and Limak Group. The 31m dam sand-gravel fill dam has a clay core and the two units are expected to produce 161 GWh/yr. A subsidiary of Limak Holding has a 49yr generation license for the plant.

Photograph courtesy of Limak Enerji
Posted 20 Sep 2008

Sirakonaklar
Location: Erzurum
Operator: 2M Enerji Toptan Elektrik Ticaret AS
Configuration: 3 X 6.1 MW Pelton
Operation: 2012
T/G supplier: Andritz
EPC: Andritz
Quick facts: This SHP is in Ispir Dist. Production is expected to be 69 GWH/yr.

Photograph courtesy of 2M Enerji Toptan Elektrik Ticaret AS
Posted 10 Mar 2013

Tatar
Location: Elazig
Operator: Darenhes Elektrik Uretimi AS
Configuration: 3 X 66.6 MW Francis
Operation: 2014
T/G supplier: Andritz
EPC: Su-Yapi, Limak
Quick facts: In Feb 2011, Darenhes Elektrik Uretimi AS, a JV of of Bilgin Enerji Yatirim Holding AS and Limak Yatirim, signed contracts with Andritz Hydro for the supply of electromechanical equipment for the Pembelik (2 X 66 MW) and Tatar (2 X 67 MW) hydropower plants on the Peri River on the border of Elaz─▒g and Tunceli provinces. Pembelik is located upstream and Tatar downstream of the existing 60-MW Seyrantepe HPP, also owned and operated by Darenhes. Tatar has a 74m clay-filled dam . Andritz supplied the T/G sets, and transformers as well as the complete electrical equipment including automation and 161kV switchyards. Preliminary construction by Limak started in 2010 and the first set was declared ready for operation in Nov 2013 followed by the second a month later. Electricity output from the multipurpose project is expected to be about 369 GWh/yr.

Photograph courtesy of Andritz
Posted 1 Jan 2015

Uzunçayır
Location: Tunceli
Operator: Limak Enerji
Configuration: 3 X 32 MW Francis
Operation: 2010
T/G supplier: Voith, Siemens
EPC: Su-Yapi, Ozgur
Quick facts: Uzunçayir is on Munzur Creek in Eastern Anatolia. The 58m sand-gravel fill dam has a clay core and a fill volume of 1.47m³. Annual output is expected to be 317 GWh. Limak has a 49yr operation license for the plant.

Photograph courtesy of Limak Enerji
Posted 20 Sep 2008

Yedisu
Location: Bingol
Operator: Ozaltin Enerji
Configuration: 3 X 7.7 MW S-turbine
Operation: 2010
T/G supplier: Andritz
EPC: Ozaltin, Nurol
Quick facts: Construction on this project began in Q1, 2008. The clay core dam is on the Firat (Euphrates) River.

Photograph courtesy of Ozaltin
Posted 20 Mar 2011