Hydroelectric Power Plants in Northern Turkey - other regions
Çalkışla
Location: Erzincan
Operator: IC-EN Elektrik Uretim ve Tic AS
Configuration: 1 X 5.94 MW, 1 X 1.88 MW spiral
Operation: 2008
T/G supplier: Kossler
EPC: Ismail Celik

Photograph courtesy of Ismail Çelik
Posted 24 Dec 2010

Çaygören
Location: Balikesir
Operator: Su Enerji A.Ş.
Configuration: 1 X 2.8 MW, 1 X 1.8 MW
Operation: 2006
T/G supplier: VA TECH
EPC: Dynelec-Sas
Quick facts: Enda Energy holds a 90% share in this IPP project and the other shareholder is Gönen HPP Electricity Generation Plc with 10%. The plant is near Sindirgi and went commercial in Jun 2006. Annual production is about 21 GWh.

Photograph courtesy of Enda Enerji Holding AŞ
Posted 23 Nov 2012

Gönen
Location: Bursa
Operator: Enda Enerji Holding AŞ
Configuration: 2 X 5.5 MW Francis
Operation: 1998
T/G supplier: Kossler
EPC: Limak
Quick facts: This is a 70m earthfill and rockfill dam. Construction on the multipurpose project started in 1986. The plant has a BOT contract with EUAS guaranteed by the Turkish Treasury.

Photograph courtesy of Enda Enerji Holding AŞ
Re-posted 23 Nov 2012

Kilickaya
Location: Sivas
Operator: Elektrik Uretim AS
Configuration: 2 x 62.5 MW Francis
Operation: 1990
T/G supplier: Resita
EPC: Romenergo, Su Yapi, Biltek
Quick facts: The Kilickaya Dam and HES was orginally built for DSI. The construction contract was signed in Oct 1980 and the project completed in May 1990. It cost $237mn. The main dam is 135m tall and has a crest length of 405m.

Photograph courtesy of Biltek
Posted 21 May 2011

Uluabat
Location: Bursa
Operator: Akenerji
Configuration: 2 X 50 MW Francis
Operation: 2010
T/G supplier: Voith, Siemens
EPC: Voith, HDM
Quick facts:In Mar 2005, Akenerji submitted the highest bid for a 49yr operating concession for the Uluabat HPP scheme associated with DSI’s Cinarcik Dam in Susurluk district. This was the first tender for a hydro project opened to private sector by EMRA. At the time, DSI was said to have completed 95% of the dam construction works. The HPP completed in Nov 2010, about 2yrs past schedule. The scheme has a 11.4km power tunnel, an 1,182m open penstock and a 1,170m tailrace channel. Akenerji invested $150mn and the project is expected to supply about 360 GWh/yr.

Photograph courtesy of www.enerjiport.com
Posted 23 Jan 2014

Uzuncayir
Location: Tunceli
Operator: Limak Enerji
Configuration: 3 X 32 MW Francis
Operation: 2009
T/G supplier: Voith, Siemens
EPC: Cemil Ozgur
Quick facts: In Dec 2007, Voith Siemens Hydro was awarded the complete equipment supply contract for this project, which was acquired in auction by the IPP Limak Insaat. The contract was worth €33mn and was undertaken by Voith companies in Austria and Turkey. DSI originally built the dam and powerhouse with space for three 24-MW sets but designers increased capacity at the existing powerhouse without costly modifications to the civil works. Voith’s supply contract covered turbines, inlet valves, governors, drainage, mechanical auxiliaries, generators, the excitation and protection system, unit and plant automation, generator bus, medium and low voltage systems, power transformers and HV (155kV) switchgear. The dam was built where the Munzur River enters Keban Reservoir.

Photograph courtesy of Voith Siemens Hydro
Posted 23 Dec 2007

   

Yeşil
Location: Sivas
Operator: Yeşilbaş AS
Configuration: 3 x 4.7 MW Francis
Operation: 2009
T/G supplier: ??
EPC: STY Insaat Turizm ve San Ltd Sti, HGG Insaat Sanayi
Quick facts: The Yesil project is on the Yesilirmak River. It went online in Dec 2009. The project was a development of Essentium (70%), STY (15%) and HGG through Yeşilbaş Enerji (15%). The plant is grid-connected via a 16km, 154kV line through the Koyulhisar HPP switchyard.

Photograph courtesy of STY
Posted 6 Mar 2011

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 28-Jan-2014

Home