Dniprodzerzhinska
Location: Dnipropetrovsk
Operator: Dniprogidroenergo
Configuration: 8 X 44 MW propeller
Operation: 1963-1964
T/G supplier: Kharkov, UETM
Quick facts: This is the fourth stage of the hydro cascade on the
Dnieper River. Annual output is about 1.4 TWh. Plant
rehabilitation is underway with World Bank funding.
Photograph courtesy of
Dniprogidroenergo
Posted 11 Jun 2005 |
Dniprovska I & II
Location: Zaporizhzhya
Operator: Dniprogidroenergo
Configuration: 9 X 72 MW Francis, 6 X 105 MW propeller
Operation: 1947-1950 (Plant I) 1974-1980 (Plant II)
T/G supplier: LMZ, GE, Kharkov
Quick facts: This is the fifth stage of the hydro cascade on the Dnieper
River. Construction started in 1927 and ten 56-MW units were put online
between 1932 and 1939. During World War II, the plant was
completely destroyed. Reconstruction began in 1944 and the first
rebuilt unit went online in in March 1947. In April 1972,
construction started on the second phase plant.
Photograph courtesy of
Dniprogidroenergo
Posted 11 Jun 2005 |
Dnister
Location: Chernivtsy
Operator: Dnisterhydroenergo
Configuration: 6 X 117 MW Kaplan
Operation: 1981-1983
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: The site is located in the middle reach of the Dnister
river, upstream of Mogilev-Podolsk. It includes earth dams flanking the center spillway and powerhouse and a 330/110kV outdoor switchyard.
Photograph courtesy of Ukrhydroproject
Posted 8 Mar 2007 |
|
Dnister Buffer
Location: Chernivtsy
Operator: Dnisterhydroenergo
Configuration: 3 X 9 MW Bulb
Operation: 1998
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: This dam forms a buffer reservoir below the main Dnister
power station.
Photograph courtesy of Ukrhydroproject
Posted 8 Mar 2007 |
Kakhovka
Location: Kherson
Operator: Dniprogidroenergo
Configuration: 3 X 59 MW propeller
Operation: 1955-1956
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: This is the lowest hydro project on the Dnieper. Average
output is 1.4 TWh/yr. Alstom supplied a new control system for the plant
in 1998.
Photograph courtesy of Ukrhydroproject
Posted 25 Mar 2007 |
Kaniv
Location: Cherkassy
Operator: Dniprogidroenergo
Configuration: 24 X 18.5 MW bulb
Operation: 1972-1975
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: This is the second stage of the hydro cascade on the
Dnieper River. Annual output is about 970 GWh. Plant
rehabilitation is underway with World Bank funding. Construction was
started on a 3.6-GW pumped-storage plant nearby, but the project was
halted in 1994 due to lack of funding.
Photograph courtesy of
Dniprogidroenergo
Posted 11 Jun 2005 |
|
Kremenchuk
Location: Cherkassy
Operator: Dniprogidroenergo
Configuration: 12 X 57 MW propeller
Operation: 1959-1960
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: This is the third stage of the hydro cascade on the Dnieper
River and the Kremenchuk Reservoir is the largest on the river
stretching for 185 km with a water surface of 2,250kmē. Annual output is about 1.5 TWh.
Photograph courtesy of
Dniprogidroenergo
Posted 26 Jun 2005 |
Kyivska HPS
Location: Kyiv
Operator: Dniprogidroenergo
Configuration: 1 X 16 MW, 3 X 22 MW, 16 X 18.5 MW bulb
Operation: 1964-1968
T/G supplier: Kharkov
EPC: Ukrhydroproject
Quick facts: This plant has integrated
abutments on both banks, a concrete dam with 20 spillways,
navigation lock, earth-fill dams and embankments, and a 110kV outdoor switchyard.
Photograph courtesy of Ukrhydroproject
Posted 25 Mar 2007 |
Kyivska HPSS
Location: Kyiv
Operator: Dniprogidroenergo
Configuration: 3 X 33.3 MW conv, 3 X 45 MW pump
Operation: 1970-1972
T/G supplier: Kharkov
Quick facts: Kyivska HPSS is located on the right bank of Kyiv
water storage 2.5km upstream from Kyivska HPS. The reservoir of Kyivska HPS acts as the lower water reservoir
for the pumped-storage plant.
Photograph courtesy of
Dniprogidroenergo
Posted 26 Jun 2005 |
|
Sabarovskaya
Location: Vinnytsya
Operator: Vinnitsaoblenergo OJSC
Configuration: 1.05 MW
Operation: ??
T/G supplier: ??
Quick facts: This plant is on a reservoir at Km 571 on the Southern
Bug River, the largest river system entirely within Ukraine's borders.
Photograph courtesy of Vinnitsaoblenergo
Posted 24 Jul 2010 |
|
Tereblja-Rikskaya
Location: Zakarpatie
Operator: Zakarpattyaoblenergo
Configuration: 3 X 9 MW
Operation: 1955
T/G supplier: UETM
EPC: Ukrhydroproject
Quick facts: This plant has integrated
abutments on both banks, a concrete spillway dam with 20 spillways,
navigation lock, earth-fill dams and embankments, and a 110kV outdoor switchyard.
Photograph courtesy of Ukrhydroproject
Posted 25 Mar 2007 |