Hydroelectric Plants in the USA - Ohio & West Virginia
Belleville
Location: WV
Operator: American Municipal Power Ohio
Configuration: 2 X 26 MW bulb
Operation: 1999
T/G supplier: Voest, Elin
Quick facts: The Belleville lock and dam complex on the Ohio River was completed in 1968. Shown under construction in upper right is the associated hydroelectric complex built about 30 years later.

Photograph by Charles Johnson and courtesy of USACE
Posted 27 Dec 2004

Greenup
Location: OH
Operator: Hamilton Electric Dept
Configuration: 3 X 23 MW bulb
Operation: 1982
T/G supplier: Neyrpic, Alstom
Quick facts: The powerhouse is on the Ohio side of the USACE Greenup lock and dam system opened in 1961. The entire generating structure is a watertight, steel-plate enclosure constructed in dry dock at St Nazaire, France. The structure was shipped across the Atlantic Ocean, unloaded, and towed to the site via the Mississippi and Ohio Rivers. Photograph courtesy of USACE
Posted 10 Apr 2005
Marmet
Location: WV
Operator: Appalachian Power Co
Configuration: 1 X 4.8 MW Francis, 2 X 4.8 propeller
Operation: 1934
T/G supplier: NN, IPM, GE
Quick facts: Twin 56ft x 360ft lock chambers and a gated dam were operational in 1934. A new 110ft x 800ft lock chamber was authorized by the Water Resources Development Act of 1996. In 2002, property acquisitions and relocations were complete and the $333mn lock construction contract was awarded.

Photograph courtesy of Waterways Council Inc
Posted 8 Feb 2006

 
Racine
Location: OH
Operator: Ohio Power Co
Configuration: 2 X 24 MW bulb
Operation: 1982-1983
T/G supplier: Sulzer Escher Wyss
Quick facts: This lock and dam complex on the Ohio River was completed in 1971.

Photograph by Charles Johnson and courtesy of USACE
Posted 27 Dec 2004

Willow Island
Location: WV
Operator: American Municipal Power Inc
Configuration: 2 X 17.5-MW bulb
Operation: 2016
T/G supplier: Voith, Siemens
EPC: MWH, Ruhlin Construction Co
Quick facts:
Willow Island Locks and Dam are near St Marys, Pleasant County, 162 river miles downstream of Point Bridge in Pittsburgh. The Willow Island project is under construction on the West Virginia side of the Ohio River, on the opposite shore of the locks. The project diverts water from the existing USACE Willow Island Locks and Dam to supply about 239 GWh/yr. A 1.6mi, 138kV transmission line connects to the PJM network. Unit-1 went commercial on 4 Jan 2016 and Unit-2 completeed the following month.

Photograph courtesy of American Municipal Power Inc
Posted 16 Jan 2016