Nuclear Power Plants in Lithuania & Ukraine
![]() |
![]() |
![]() |
|
Chernobyl Location: Ukraine Operator: Energoatom Configuration: 4 X 925 MW RBMK Operation: 1978-1982 (ret) Reactor supplier: Mintyazhmash T/G supplier: Kharkov Quick facts: In 1970, construction began on what was planned to be one of the world’s largest nuclear power plants with six RBMK-1000 reactors. In Apr 1986, Unit-4 was destroyed in a catastrophic accident. Despite this, several units were put back online until Unit-3 was finally shutdown in Dec 2000. Unit-5 was nearly complete at the time of the accident. A massive steel confinement structure is being designed to enclose the remains of Unit-4.
Photograph courtesy of Energoatom |
Crimea Location: Ukraine Operator: Ministry of Fuel and Energy Configuration: 2 X 1,000 MW PWR Operation: n/a (terminated 1989) Reactor supplier: Mintyazhmash T/G supplier: ?? EPC: Atomenergoproekt Quick facts: Construction at Crimea NPP in Schelkino began in 1976 and when the project was stopped in 1989, about $1b had been spent. Engineering work was essentially complete, but after the Chernobyl accident, seismic concerns at the Crimea site resurfaced and work was stopped. Unit-1 was said to be 80% complete and Unit-2 18% finished. The reactors were VVER-1000/320 models. The formal cancellation was in Jun 2000. In 2004, the Ministry of Fuel and Energy gifted the remains to the Crimea Republic with instruction to dispose of the material and use the proceeds for social investments. Part of the site may be reused for a new CCGT power station.
Photograph courtesy of istpravda.com.ua |
Ignalina
Photograph courtesy of Ignalina NPP |
![]() |
![]() |
![]() |
|
Khmelnitsky Location: Ukraine Operator: Energoatom Configuration: 2 X 1,000 MW PWR Operation: 1988-2004 Reactor supplier: Mintyazhmash T/G supplier: LMZ, Electrosila EPC: EnergoProekt Kyiv Quick facts: This plant is in Slavutsky district near the Goryn River in western Ukraine. In 1981, construction got underway and the first unit was put online in late 1987. Sites for three more units were cleared and construction on Unit-2 began in 1983 with plans to finish it in 1991. In 1990, however, construction was stopped as part of a moratorium on new plant construction adopted by Verkhovna Rada. After the moratorium was lifted, construction proceeded very slowly and was finally completed in Aug 2004. Units 3&4 are planned for completion by 2020.
Photograph courtesy of Energoatom |
Rivne Location: Ukraine Operator: Energoatom Configuration: 2 X 400 MW, 2 X 1,000 PWR Operation: 1981-2004 Reactor supplier: Mintyazhmash T/G supplier: Kharkov, LMZ EPC: EnergoProekt Kyiv Quick facts: Design of Rivne began in 1971 and this was the first nuclear power plant with the VVER-440, B-213 reactors. Construction started in 1973. The construction of Unit-4 started in 1984 with plans for completion in 1991 but construction was suspended in that year and did not resume until 1993. Engineering assistance was provided by EDF and Fortum and Unit-4 was put online in Oct 2004.
Photograph courtesy of Energoatom |
South Ukraine Location: Ukraine Operator: Energoatom Configuration: 3 X 1,000 MW PWR Operation: 1983-1989 Reactor supplier: Mintyazhmash T/G supplier: Kharkov EPC: EnergoProekt Kharkov Quick facts: The South-Ukraine power complex is located on the South Bun river in Mykolaiv region and consists of the NPP, a small conventional hydroelectric plant, and a pumped-storage plant. Construction of the nuclear plant and satellite town of Yuzhno-Ukrainsk started in 1975 and Unit-1 was connected in Dec 1982 after 72 months of construction. The 25-MW Olexandrivska hydro plant was finally completed in 1999 after years of delay and the first 150-MW unit at the Tashlyk pumped-storage plant in late 2006.
Photograph courtesy of Energoatom |
![]() |
||
|
Zaporizhzhya Location: Ukraine Operator: Energoatom Configuration: 6 X 1,000 MW PWR Operation: 1984-1995 Reactor supplier: Mintyazhmash T/G supplier: Kharkov EPC: Atomenergoproekt, Ministry of Power Stations (USSR) Quick facts: ZNPP is situated in the steppe zone of Ukraine on Kakhovsky reservoir. It is the largest nuclear power station in Europe. The construction decision was made in 1978 and work got underway in 1981. The plant produces up to 38 TWh/yr, or about 50% of electricity generated at Ukrainian NPPs. ZNPP is the first Ukrainian nuclear power plant with onsite fuel dry storage. <
font size="1" face="Arial">Photograph courtesy of Energoatom |
||
![]() |
![]() |
Data: industcards, Platts UDI World Electric Power Plants Data Base
Updated 06/26/11