Solar Power Plants in Spain - other regions
![]() |
![]() |
![]() |
|
Arnedo
Photograph courtesy of Grupo T-Solar |
Barcelona Culture Center
Photograph courtesy of
Phönix SonnenStrom AG
|
Beneixama Location: Alicante Operator: City Solar Configuration: 20 MWp Operation: 2007 System supplier: Q-Cells EPC: City Solar Quick facts: This facility consists of 200 modules, each with 80, 100-kWp subsystems. The first phase was completed to schedule in Feb 2007. The construction workforce was about 100 people, most from local companies. In total, Beneixama has about 100,000 City Solar PQ 200 crystalline modules equipped with cells from Q-Cells produced by its partners Aleo, Solon, and Tenesol. The arrays cover 500,000m² in an area 3km from Beneixama, inland from the Costa Blanca. Annual global radiation incident at the module level is 1,934 kWh/m². Average output is expected to be 30 GWh/yr. Siemens was responsible for the electrical equipment including wiring, transformers, and inverters.
Photograph courtesy of
City Solar AG |
![]() |
![]() |
![]() |
|
La Seca
Photograph courtesy of Grupo T-Solar |
Finca La Portuguesa Location: Badajoz Operator: Grupo OPDE Configuration: 3.4 MWp Operation: 2007 System supplier: Mecasolar Quick facts: This is one of a growing number of solar tracking PV plants built by OPDE.
Photograph courtesy of
Grupo OPDE |
La Dehesica I Location: Albacete Operator: Anbelo Solar SL Configuration: 1.848 MWp Operation: 2007 System supplier: Gruposolar Quick facts: Development of this plant was agreed with the municipality of La Roda in Apr 2007. An extension of 2.08 MW is under construction for service in 2008.
Photograph courtesy of
Anbelo Solar SL |
![]() |
![]() |
![]() |
|
Olmedilla de Alarcon Location: Cuenca Operator: Nobesol Configuration: 60 MWp Operation: 2008 System supplier: ?? EPC: Nobesol Quick facts: This plant has 162,000 PV panels and was completed in 15mos at a cost of €385mn. When put in service in Jun 2008, it became the largest solar PV power station in the world.
Photograph courtesy of Nobesol |
Salvia-Garrofe Location: Lerida Operator: AE3000 Configuration: 113 kWp Operation: 2006 System supplier: Sanyo Quick facts: This plant in Palau d’Anglesola was connected to the grid on 29 Dec 2006. The installation has 540, 210W HIP210-NHE5 modules, 18 Deger Energie 5000EL solar trackers, and 18 SMA inverters.
Photograph courtesy of
AE3000 |
Sanfeliu Location: Lerida Operator: AE3000 Configuration: 227 kWp Operation: 2006 System supplier: Sanyo Quick facts: This plant in Bellpuig was connected on 23 Dec 2006. The installation has1,080, 210W HIP210-NHE5 modules, 36 Deger Energie 5000EL solar trackers, and 36 SMA inverters.
Photograph courtesy of
AE3000 |
![]() |
![]() |
![]() |
|
Tietar Location: Cáceres Operator: Grupo OPDE Configuration: 1.563 MWp Operation: 2008 System supplier: Mecasolar Quick facts: This plant has 140, 11-kWp trackers with estimated production of 2,000 kWh/kWp installed. Tietar is very close to the 20-MW Almaraz and 2.5-MW Belvis de Monroy solar plants. Photograph courtesy of Grupo OPDE |
Toledo Solar
Photograph courtesy of
Union Fenosa |
Zaragoza Opel Factory Location: Zaragoza Operator: Clairvoyant Energy Configuration: 11.8 MWp Operation: 2008 System supplier: United Solar Ovonic Quick facts: This roof-top installation has 85,000 PV laminates and was the world's largest rooftop system at completion. It was jointly developed with Veolia Environment, and the Aragon regional government. Annual production is expected to be 15.1 GWh.
Photograph courtesy of
United Solar Ovonic LLC |
![]() |
||
Data: industcards, Platts UDI World Electric Power Plants Data Base
Updated 03/13/10