Anhui Bengbu
Location: Anhui
Operator: China Guodian Corp
Configuration: 2 X 600 MW
Operation: 2008-2009
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: ??
EPC: SEPCO, Anhui Electrical Power Construction No 1 Co
Quick facts: Anhui Bengbu was approved by NDRC in Mar 2007. The site is on
the Huaihe River 38km from Bengbu's urban area. The supercritical power station cost
4.32bn yuan and is a joint investment of China Guodian (55%),
Anhui Province Energy Group (35%), and Bengbu Construction Investment (10%). Unit-1
went commercial on 30 Dec 2008 after 19mos and 5 days of construction
followed by Unit-2 on 20 Apr 2009.
Photograph courtesy of China Guodian Corp
Posted 29 May 2010 |
Anhui Tongling
Location: Anhui
Operator: Guodian Tongling Power Generation Co Ltd
Configuration: 2 X 600 MW
Operation: 2008
Fuel: coal
Boiler supplier: Dongfang
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This genco was established in Apr 2004. In Feb 2007, construction of two 600-MW supercritical
units was approved with a total investment of 4.65bn yuan. The project started construction on 28 Mar 2007 and commissioned on 28 Sep 2008.
The first of 1,000-MW units to extend the site went online in Mar 2011.
Photograph courtesy of China Guodian Corp
Posted 30 May 2010 |
Anqing
Location: Anhui
Operator: Anhui Electric Power Corp
Configuration: 2 X 300 MW
Operation: 2005
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: Dongfang
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: In Feb 1999, the Export-Import Bank of Japan signed an untied
loan totaling up to ¥44.75bn with the Bank of China to finance
construction of this power plant on the Yangtze in Anqing City. Two more
300-MW sets are planned.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 22 Mar 2008 |
 |
 |
 |
|
Chizhou
Location: Anhui
Operator: Anhui Chizhou Jiuhua Power Generation Co
Configuration: 2 X 300 MW
Operation: 2005
Fuel: bituminous coal Boiler supplier: ??
T/G supplier: ??
EPC: China Power Complete Equipment Co, Anhui Electrical Power Construction No 1 Co
Quick facts: Construction at Chizhou started on 11 Nov 2003 and the units went commercial
on 11 Sep 2005 and 8 Dec 2005, respectively. The plant is owned by China Huadian Corp (40%), Anhui Province Energy Group Co (35%),
Shenergy Co (20%), and Anhui Kangyuan Electric & Heat Power Co (5%). Chizhou had the first FGD scrubbers in the province.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 22 Mar 2008 |
Hefei-2
Location: Anhui
Operator: Anhui Hefei United Power Generation Ltd
Configuration: 2 X 350 MW
Operation: 2001
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: Alstom
EPC: Anhui Electric Power Design Inst, Anhui Electrical Power Construction No 1 Co
Quick facts: This plant was ordered in 1997 by a consortium including the
local power company, government authorities of Hefei City and Anhui
Province, and the overseas investor United Engineers (Singapore) Pte Ltd.
The plant is fueled with coal from a neighboring mine.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 22 Mar 2008 |
Fengtai
Location: Anhui
Operator: Huainan Huaizhe Coal and Electricity Integration Project
Configuration: 2 X 600 MW
Operation: 2008
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: East China Electric Power Design Institute, Anhui Electrical Power Construction No 2 Co, Zhejiang Electric Power Construction
Quick facts: In Sep 2006, construction began at the Fengtai power station on the Huai River in Huainan City. The supercritical project is a 50:50 JV of Zhejiang Energy Group and Huainan Mining Group and is a cooperative coal-by-wire venture based on Anhui's Huainan coalfield, which has about 300bn tons of coal and is the nearest big coalfield to Zhejiang. The first 1,200-MW phase of the Fengtai project was built near the Gubei Coal Mine, which will supply 6mn tpy of fuel. Unit-2 went commercial in Sep 2008, thereby completing Phase-I.
Photograph courtesy of Anhui Electrical Power Construction No 2 Co
Posted 22 Nov 2011 |
 |
 |
 |
|
Fuyang Huaren
Location: Anhui
Operator: Fuyang China Resources Power Co Ltd
Configuration: 2 X 640 MW
Operation: 2006
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: CR Power owns a 55% equity interest in Fuyang power station. Construction started in Apr 2004 and the two
supercritical units commenced commercial operations in Mar and Jun 2006,
respectively. Electricity is sold to the Anhui provincial power grid and delivered via Eastern China Power Grid Co Ltd.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 22 Mar 2008 |
Huaibei-2
Location: Anhui
Operator: Huaibei Guoan Power Co Ltd
Configuration: 2 X 320 MW
Operation: 2004-2005
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: ??
Quick facts: This operating company was established in 1997 and is
owned by Anhui Electric Power (40%), SDIC ( 35%), and Xing Holdings Ltd
(30%). The units were uprated from 300 MW.
Photograph courtesy of SDIC Huajing Power Holdings Co Ltd
Posted 14 Mar 2010 |
Huadian Suzhou
Location: Anhui
Operator: Anhui Huadian Suzhou Power Generation Co Ltd
Configuration: 2 X 600 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This plant is 97% owned by Huadian Power International Corp
and two more 600-MW sets are planned. The first two supercritical units have
FGD systems from Insigma Mechanical & Electrical Engineering.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 23 Mar 2008 |
 |
 |
 |
|
Huadian Wuhu
Location: Anhui
Operator: China Power Investment Corp
Configuration: 2 X 660 MW
Operation: 2008
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 13 Apr 2008 |
Huainan Tianji
Location: Anhui
Operator: China Power Investment Corp
Configuration: 2 X 600 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: Ground-breaking was on 22 Jul 2005 and the first unit was
handed over on 3 Aug 2007. These two supercritical units had a total
investment budget of RMB 5.34bn RMB, Shanghai Electric Power Co Ltd and
Huainan Mine Co Ltd are joint owners.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 13 Apr 2008 |
Huaneng Chaohu
Location: Anhui
Operator: Huaneng Power International Inc
Configuration: 2 X 600 MW
Operation: 2008
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: Harbin
EPC: Anhui Electrical Power Construction No 2 Co, China Construction Second Engineering Bureau
Quick facts: In Jun 2007, the foundation stone was laid for the supercritical Chaohu power station in Jucao District, Caohu City. This was Huaneng Power's first project in Anhui. The second unit completed in Nov 2008.
Photograph courtesy of Anhui Electrical Power Construction No 2 Co
Posted 22 Nov 2011 |
 |
 |
 |
Maanshan Works
Location: Anhui
Operator: Maanshan Iron and Steel Co Ltd
Configuration: 1 X 135 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: ??
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This captive power plant also has a 150-MW single-shaft,
blast furnace gas fired combined-cycle set built by Mitsubishi Heavy
Industries in 2007.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 13 Apr 2008
|
Pingwei
Location: Anhui
Operator: China Power Investment Corp
Configuration: 2 X 600 MW, 2 X 640 MW
Operation: 1989-2007
Fuel: bituminous coal
Boiler supplier: ABB, Mitsui Babcock, Harbin
T/G supplier: Harbin, Alstom Beizhong Power
EPC: Ebasco, China Machine Building International
Quick facts: Pingwei has China's first domestically-produced 600-MW unit.
Pingwei-4 went commercial on 24 Nov 2007.
Photograph courtesy of China Power Investment Corp
Posted 10 Oct 2010
|
Tongling
Location: Anhui
Operator: Anhui Tongling Power Generation Co Ltd
Configuration: 2 X 125 MW, 2 X 300 MW
Operation: 1988-1999
Fuel: bituminous coal
Boiler supplier: Shanghai, Harbin
T/G supplier: Shanghai, Harbin
EPC: China Power Complete Equipment Co, Anhui Electrical Power Construction No 1 Co
Quick facts: The 300-MW units have wet limestone scrubbers from Marsulex
and China Huadian Engineering and SCRs from Beijing Guodian Longyuan
Environment Protection.
Photograph courtesy of Anhui Electrical Power Construction No 1 Co
Posted 22 Mar 2008
|
| |
 |
|
|
|
Xuancheng
Location: Anhui
Operator: SDIC Huajing Power Holdings Co Ltd
Configuration: 1 X 600 MW
Operation: 2009
Fuel: bituminous coal
Boiler supplier: Harbin, Doosan
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This is an ultrasupercritical unit. Two more sets are
planned.
Photograph courtesy of SDIC Huajing Power Holdings Co Ltd
Posted 21 May 2011 |
|
 |