Anqing
Location: Anhui
Operator: Anhui Electric Power Corp
Configuration: 2 X 300 MW
Operation: 2005
Fuel: bituminous coal Boiler supplier: Shanghai
T/G supplier: Dongfang
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: In Feb 1999, the Export-Import Bank of Japan signed an untied
loan totaling up to ¥44.75bn with the Bank of China to finance
construction of this power plant on the Yangtze in Anqing City. Two more
300-MW sets are planned.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 22 Mar 2008 |
Chizhou
Location: Anhui
Operator: Anhui Chizhou Jiuhua Power Generation Co
Configuration: 2 X 300 MW
Operation: 2005
Fuel: bituminous coal Boiler supplier: ??
T/G supplier: ??
EPC: China Power Complete Equipment Co, Anhui Electrical Power Construction No 1 Co
Quick facts: Construction at Chizhou started on 11 Nov 2003 and the units went commercial
on 11 Sep 2005 and 8 Dec 2005, respectively. The plant is owned by China Huadian Corp (40%), Anhui Province Energy Group Co (35%),
Shenergy Co (20%), and Anhui Kangyuan Electric & Heat Power Co (5%). Chizhou has the first FGD scrubbers in the province.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 22 Mar 2008 |
Hefei-2
Location: Anhui
Operator: Anhui Hefei United Power Generation Ltd
Configuration: 2 X 350 MW
Operation: 2001
Fuel: bituminous coal Boiler supplier: Harbin
T/G supplier: Alstom
EPC: Anhui Electric Power Design Inst, Anhui Electrical Power Construction No 1 Co
Quick facts: This plant was ordered in 1997 by a consortium including the
local power company, government authorities of Hefei City and Anhui
Province, and the overseas investor United Engineers (Singapore) Pte Ltd.
The plant is fueled with coal from a neighboring mine. A 600-MW
supercritical set is being added to the site.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 22 Mar 2008 |
|
Fuyang Huaren
Location: Anhui
Operator: Fuyang China Resources Power Co Ltd
Configuration: 2 X 640 MW
Operation: 2006
Fuel: bituminous coal Boiler supplier: Harbin
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: CR Power owns a 55% equity interest in Fuyang power station. Construction started in Apr 2004 and the two
supercritical units commenced commercial operations in Mar and Jun 2006,
respectively. Electricity is sold to the Anhui provincial power
grid and delivered via Eastern China Power Grid Co Ltd
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 22 Mar 2008 |
Guodian Tongling
Location: Anhui
Operator: Guodian Tongling Power Generation Co Ltd
Configuration: 2 X 125 MW, 2 X 300 MW
Operation: 1988-1999
Fuel: bituminous coal Boiler supplier: Shanghai
T/G supplier: Shanghai, Harbin
EPC: China Power Complete Equipment Co, Anhui Electrical Power Construction No 1 Co
Quick facts: The 300-MW units have wet limestone scrubbers from Marsulex
and China Huadian Engineering and SCRs from Beijing Guodian Longyuan
Environment Protection. A 600-MW supercritical set is being added to the
site.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 22 Mar 2008 |
Huadian Suzhou
Location: Anhui
Operator: Anhui Huadian Suzhou Power Generation Co Ltd
Configuration: 2 X 600 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This plant is 97% owned by Huadian Power International Corp
and
two more 600-MW sets are planned. The first two supercritical units have
FGD systems from Insigma Mechanical & Electrical Engineering.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 23 Mar 2008 |
|
Huadian Wuhu
Location: Anhui
Operator: China Power Investment Corp
Configuration: 2 X 660 MW
Operation: 2008
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 13 Apr 2008 |
Huainan Tianji
Location: Anhui
Operator: China Power Investment Corp
Configuration: 2 X 600 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: Ground-breaking was on 22 Jul 2005 and the first unit was
handed over on 3 Aug 2007. These two supercritical units had a total
investment budget of RMB 5.34bn RMB, Shanghai Electric Power Co Ltd and
Huainan Mine Co Ltd are joint owners.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 13 Apr 2008 |
Maanshan Works
Location: Anhui
Operator: Maanshan Iron and Steel Co Ltd
Configuration: 1 X 135 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: ??
T/G supplier: ??
EPC: Anhui Electrical Power Construction No 1 Co
Quick facts: This captive power plant also has a 150-MW single-shaft,
blast furnace gas fired combined-cycle set built by Mitsubishi Heavy
Industries in 2007.
Photograph courtesy of Anhui Electrical
Power Construction No 1 Co
Posted 13 Apr 2008 |