Chaozhou Sanbaimen
Location: Guangdong
Operator: Datang International Power Generation Co Ltd
Configuration: 2 X 600 MW
Operation: 2006
Fuel: bituminous coal
Boiler supplier: Mitsui Babcock Harbin Boiler Co
T/G supplier: ??
EPC: Northeast China International Electric Power Corp
Quick facts: This power station is in the Sanbaimen Port EDZ in Zhelin
Town, Raoping County. The two supercritical units have ESPs, wet limestone
FGDs, and low-Nox burners. A 50,000t coal coal unloading facility was
built and the plant is connected to the grid at 220kV. Chaozhou cost RMB
5.9bn and is jointly owned with Wenshan Guoneng Investment Co and Chaozhou
Xinghua Energy Investment Co. In Nov 2006, two 1,000-MW units were
ordered from Harbin for the Chaozhou plant.
Photograph courtesy of Guangdong China Business News Network
Re-posted 17 Apr 2010 |
Guangzhou Nansha Phase II
Location: Guangdong
Operator: China Resources Power Holdings Co Ltd
Configuration: 2 X 300 MW CHP
Operation: 2009
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: Dongfang
Quick facts: In Jan 2006, China Resources Power established a new subsidiary to build a cogen plant complex in Guangzhou’s Nansha Economic and Technological Development Zone in the center of the Pearl River delta. Nearby industrial complexes include automotive suppliers, chemical plants, the Nansha International Business Center and other heating services customers. Two 180-MW CCGT blocks were built first, followed by the coal units.
Photograph by 性情盅人 (Panaramio)
Posted 22 Oct 2011 |
Huaneng Haimen
Location: Guangdong
Operator: Huaneng Power International
Configuration: 2 X 1,036 MW
Operation: 2009-2010
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: Hitachi, Dongfang
EPC: Guangdong Electric Power Design Institute
Quick facts: These units have Alstom seawater FGD systems.
Photograph courtesy of Guangdong Electric Power Design Institute
Posted 24 Aug 2011 |
|  |
 |
Huaneng Shantou
Location: Guangdong
Operator: Huaneng Power International
Configuration: 2 X 300 MW, 1 X 600 MW
Operation: 1996-2005
Fuel: bituminous coal
Boiler supplier: Dongfang, Babcock-Hitachi
Dongfang Boiler Co
T/G supplier: LMZ, Electrosila
EPC: Guangdong Electric Power Design Institute, Northwest Electric Power
Design Institute
Quick facts: This plant is on the outskirts of Shantou City. The first two
sets have boilers supplied by Dongfang using technology from Foster
Wheeler and Russian-made turbines and generators. The two units went
commercial on 1 Jan 1997. Unit-3 was approved in Mar 2003,
construction started on 1 Mar 2004, and the set went commercial on 20 Oct
2005. Coal is mostly from northern Shanxi, transported by rail from the
mines to Qinhuangdao port, and then by ship down the east coast of China
to a jetty at the plant owned and maintained by the Shantou Port
Authority.
Photograph courtesy of Huaneng Power
Posted 12 Jan 2010 |
Heyuan
Location: Guangdong
Operator: Shenzhen Energy Co
Configuration: 2 X 622 MW
Operation: 2009
Fuel: coal
Boiler supplier: MHI, Harbin
T/G supplier: MHI, Harbin
EPC: Central Southern China Electric Power Design Institute, SEPCO
Quick facts: The Heyuan site is in Yuancheng District, Heyuan City, 200km
north of Shenzhen. The first-phase project was approved in Feb 2007 for an
investment of Rmb 5.3bn. These are among the fist ultrasupercritical sets
in China and were jointly manufactured by Harbin and MHI.
Photograph courtesy of Shezhen Energy Co
Posted 1 Jun 2011 |
Jinwan
Location: Guangdong
Operator: Guangdong Yuedian Group
Configuration: 2 X 600 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: Shanghai
Quick facts: Jinwan is located in Zhuhai’s Gaolan Port Economic Zone. The
two supercritical units are jointly invested by Guangdong Yuedian and CKI
Holdings. Two 1,000-MW sets are planned for the site.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
 |
 |
 |
|
Maoming 5&6
Location: Guangdong
Operator: Guangdong Yuedian Group
Configuration: 1 X 210 MW, 1 X 300 MW CHP
Operation: 2003-2006
Fuel: bituminous coal
Boiler supplier: Harbin, Dongfang
T/G supplier: ??
Quick facts: Maoming's first units (2 X 25 MW) were built with Soviet
assistance. These and 3 X 100 MW follow-on units are now all retired. A
600-MW set is planned for the site.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
Mawan
Location: Guangdong
Operator: Shenzhen Energy Group Co Ltd
Configuration: 6 X 300 MW
Operation: 1993-2003
Fuel: coal
Boiler supplier: Harbin
T/G supplier: Harbin
EPC: North China Electric Power Design Institute, Guangdong Power
Engineering Corp, Harbin
Quick facts: Unit-4 has the first domestically-made saltwater FGD scrubber
in China. Unit-1 was retrofit with plasma ignition and low NOx combustion technology
by Yantai Longyuan Power Technology.
Photograph courtesy of Shezhen Energy Co
Posted 30 May 2011 |
Nanhai
Location: Guangdong
Operator: Kingsun Energy
Configuration: 2 X 200 MW, 2 X 300 MW, 1 X 600 MW CHP
Operation: 2005-2009
Fuel: coal, coal-water slurry
Boiler supplier: ??
T/G supplier: ??
EPC: Hubei Second Electric Power Construction Engineering Co
Quick facts: The 200-MW units at Nanhai are the largest purpose-built,
coal water slurry boilers in the world.
Photograph courtesy of Hubei Second Electric Power Construction Engineering Co
Posted 1 May 2011 |
 |
 |
 |
|
Pinghai
Location: Guangdong
Operator: Guangdong Electric Power Development Co
Configuration: 2 X 1,000 MW
Operation: 2010
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: ??
EPC: Guangdong Electric Power Design Institute
Quick facts: Construction started on 22 Dec 2008 at this site in Huidong County, Huizhou City, and
the first unit went commercial on 5 Oct 2010.
There are five investors and total investment in the two units is expected
to be Rmb 8.5bn. Four more 1,000-MW sets are planned. Design fuel is
Indonesian coal and Zhungeer coal. SO3 FGC systems are installed.
Photograph courtesy of Huidong County Government
Re-posted 27 Dec 2010 |
Shajiao-B
Location: Guangdong
Operator: Shenzhen Guangshen Shajiao B Power Co Ltd
Configuration: 2 X 350 MW
Operation: 1987
Fuel: bituminous coal
Boiler supplier: IHI
T/G supplier: Toshiba
EPC: Ove Arup, Ewbank Preece, Guangdong Electric Power Design Institute, Hopewell Construction, Slipform Engineering
Quick facts: In 1979, Hopewell Holdings and Japanese trading company
Kanematsu-Gosho proposed to Guangzhou City development of a 2 X 250 MW
power station. The original plan did not advance, although Guangdong
Province later built the first phase of Shajiao-A. The
Hopewell project turned into Shajiao-B built for Shenzhen SEZ as one of
the first BOT schemes in China. At completion, shareholders were Hopewell Holdings, China
Development Investment, an affiliate of Bank of China, Kanematsu-Gosho
Ltd, Yue Xiu Enterprises Ltd, and Shum Yip Development Co Ltd.
Construction started on 1 Jul 1985 and Unit-1 was synchronized on 22 Apr
1987 followed by Unit-2 on 22 Jul 1987. Shajiao-B cost about $513mn.
Photograph courtesy of Hopewell Power (China) Ltd
Posted 5 Apr 2008 |
Shajiao-A
Location: Guangdong
Operator: Guangdong Yuedian Group
Configuration: 3 X 210 MW, 2 X 300 MW
Operation: 1987-1993
Fuel: bituminous coal
Boiler supplier: Harbin, Shanghai
T/G supplier: Shanghai
EPC: Guangdong Electric Power Design Institute
Quick facts: Project construction at Shajiao-A started in Oct 1984 and the
first unit went online in Apr 1987. The first three sets were uprated to
210 MW. All 5 units have been retrofit with FGD scrubbers. Two 1,000-MW
sets are planned for the site.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
 |
 |
 |
|
Shajiao-C
Location: Guangdong
Operator: Guangdong Guanghope Power Co
Configuration: 3 X 660 MW
Operation: 1995-1996
Fuel: bituminous coal
Boiler supplier: ABB
T/G supplier: G-A
EPC: G-A, Slipform Engineering, Ove Arup
Quick facts: Shajiao-C is on the Pearl River 60km from Guangzhou. Unit-1
was synchronized in 32mos. The "C" station was one of several Chinese plants
developed and built by Hopewell Holdings, a property and infrastructure
company founded in 1963. In 1993, Hopewell formed and listed Consolidated Electric Power Asia Ltd (CEPA). In 1997, Hopewell sold sold its
interest in CEPA to Southern Energy Asia Inc, a subsidiary of Southern
Company from the USA that was later spun off as Mirant. In 2002, CR Power spent $300mn to buy the ownership interest of Mirant.
In Oct 2006, Insigma Engineering completed the last of three new FGD
scubbers of Alstom design at Shajiao-C. The FGD project contract was
signed in Feb 2004.
Photograph courtesy of China Resources Power Holdings Co
Posted 12 Feb 2004 |
Shanwei Dongzhou
Location: Guangdong
Operator: Guangdong Electric Power Development CO
Configuration: 2 X 600 MW
Operation: 2008
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler
T/G supplier: ??
Quick facts: Two 660-MW supercritical sets are under construction at
Shanwei Dongzhou and four 1,000-MW USC sets are planned.
Photograph courtesy of Guangdong Yuedian Group
Posted 6 Jun 2010 |
Sinopec Maoming
Location: Guangdong
Operator: Sinopec
Configuration: 2 X 50 MW, 2 X 100 MW
Operation: 1995-2006
Fuel: petroleum coke, bituminous coal
Boiler supplier: Ahlstrom, FW
T/G supplier: ??
EPC: G-A, Slipform Engineering, Ove Arup
Quick facts: These units at a petrochemical works are among two dozen FW
ACFB boilers purchased by Sinopec to power its operations in various
locations. In early 2008, the 100-MW sets set continuous operation records
for similar equipment in China. Unit-1 ran for 640 days straight and
Unit-2 for 540 days.
Photograph courtesy of Foster Wheeler
Posted 19 Apr 2008 |
 |
 |
 |
|
Taishan
Location: Guangdong
Operator: Shenhua Guohua Power
Configuration: 5 X 600 MW
Operation: 2003-2006
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: Shanghai
EPC: Guangdong Electric Power Design Institute, Tianjin Electric Power Construction
Quick facts: This site is sized for eight 600-MW units. Unit-2 went
commercial on 9 Apr 2004, Unit-3 on 21 Jan 2006, and Unit-5 on 14
Dec 2006.
Photograph courtesy of Guangdong Provincial People's Network Information Center
Posted 14 Feb 2010 |
Yuehua 5&6
Location: Guangdong
Operator: Guangdong Electric Power Development CO
Configuration: 2 X 300 MW
Operation: 1989-1990
Fuel: bituminous coal
Boiler supplier: Shanghai
T/G supplier: Shanghai
EPC: Guangdong Electric Power Design Institute
Quick facts: Yuehua in Huangpu District, Guangzhou City, had four 125-MW
oil-fired units online from 1977-1980. These were retired in 2008-2009.
The plant is invested by Guangdong Yuedian (51%) and China Huaneng (49%).
Photograph courtesy of Guangdong Yuedian Group
Posted 6 Jun 2010 |
Yueyang
Location: Guangdong
Operator: Guangdong Electric Power Development Co Ltd
Configuration: 2 X 25 MW, 1 X 135 MW
Operation: 1991-2006
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
EPC: Guangdong Electric Power Design Institute
Quick facts: This power plant is in Yangshan County, Qingyuan City.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
 |
 |
 |
|
Yunfu
Location: Guangdong
Operator: Guangdong Electric Power Development Co Ltd
Configuration: 2 X 125 MW, 2 X 135 MW
Operation: 1989-2002
Fuel: anthracite
Boiler supplier: Shanghai, Dongfang
T/G supplier: ??
EPC: Guangdong Electric Power Design Institute
Quick facts: This power station in Hekou Town, Yunfu City was expanded with two 300-MW sets.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
Zhanjiang
Location: Guangdong
Operator: Guangdong Electric Power Development Co Ltd
Configuration: 4 X 300 MW, 2 X 600 MW
Operation: 1995-2006
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Guangdong Electric Power Design Institute
Quick facts: This power station in Chiklan District, Zhanjiang City, was
built in two phases. The first phase is invested by Guangdong EPD (76%)
and Guohua Energy (24%) and was retrofit with FGD systems in 2007 at a
cost of Rmb 510mn. The 600-MW units were built to burn orimulsion by
Petroleum Fuel Oil Co, Guangdong EPD and Zhanjiang Port Group Co. Most of
the shareholdings are now by Guangdong EPD. The 600-MW sets were converted
to coal in 2010.
Photograph courtesy of Guangdong Yuedian Group
Posted 5 Jun 2010 |
Zhuhai 1&2
Guangdong
Operator: Cheung Kong Infrastructure
Configuration: 2 X 700 MW
Operation: 2000-2001
Fuel: coal
Boiler supplier: MHI
T/G supplier: Westinghouse
EPC: Washington Group International
Quick factQuick facts: Two 600-MW supercritical units were added in 2007.
Photograph courtesy of Washington Group Intl
Posted 21 Oct 2001 |
 |