Coal-Fired Plants in China - Henan

Dengfeng
Location: Henan
Operator: China Resources Power Holdings Co
Configuration: 2 X 300 MW
Operation: 2004
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
Quick facts: Dengfeng is 85% owned by CR Power. Construction started in Dec 2002 and took approximately 20 months, about 6 months ahead of the average construction time for similar generation units in the Chinese power industry.

Photograph courtesy of China Resources Power Holdings Co
Posted 6 Nov 2004

Hebi Wanhe/Hebi Fenghe
Location: Henan
Operator: Hebi Wanhe Electric Power Co Ltd/Hebi Fung Hok Power Co Ltd
Configuration: 2 X 200 MW, 2 X 300 MW, 2 X 600 MW
Operation: 1991-2007
Fuel: coal
Boiler supplier: Harbin, Dongfang, BHDB
T/G supplier: ??
EPC: Henan No 1 Thermal Power Construction, Henan Construction Group II.

Photograph by 鹤壁电厂 (Panoramio)
Posted 17 Jul 2010

Huaneng Qinbei
Location: Henan
Operator: Huaneng Power International Inc
Configuration: 4 X 600 MW
Operation: 2004-2008
Fuel: coal
Boiler supplier: BHDB, Dongfang
T/G supplier: Harbin
EPC: Henan Construction Group II
Quick facts: Unit-1 was the first domestically-made 600-MW supercritical coal-fired generating unit put into operation. In Jun 2007, HPI received approval to extend the Qinbei plant with Units 3&4. The project cost approximately RMB4.48, of which 20% was equity capital funded by HPI (60%), Henan Provincial Construction Investment Corp (35%), and Jiyuan Municipal Construction Investment Corp (5%), with the remaining funded by bank loans. In Dec 2010, HPI was approved to add the first of two 1,000-MW sets at Qinbei.

Photograph courtesy of Henan Construction Group II
Posted 17 Jul 2010

Luohe-2
Location: Henan
Operator: Huadian Power International Corp Ltd
Configuration: 2 X 300 MW CHP
Operation: 2010
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: ??
EPC: SEPCO
Quick facts: Huadian is a 75% owner of this plant. Unit-1 went online on 14 Jul 2010.

Photograph courtesy of Henan Land Cement Co
Posted 5 Dec 2010

Pingdingshan
Location: Henan
Operator: China Power Investment Corp
Configuration: 1 X 50 MW, 2 X 210 MW
Operation: ??-2006
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
Quick facts: The 210-MW units have wet limestone scrubbers from CPI Yuanda.

Photograph courtesy of CPI Yuanda Environmental
Posted 30 Dec 2007

Pingdingshan Luyang
Location: Henan
Operator: China Power Investment Corp
Configuration: 2 X 1,000 MW
Operation: 2010
Fuel: bituminous coal
Boiler supplier: Donfang
T/G supplier: Harbin
EPC: Henan No 1 Thermal Power Construction Co
Quick facts: These USC units are CPI's first 1-GW sets in inland China. The site plan calls for six units to be built in partnership with Pingdingshan Coal Co Ltd. Unit-1 is the first installation of Emerson’s Ovation system for direct turbine control in a 1,000-MW set.

Photograph courtesy of Henan Land Cement Co
Posted 5 Dec 2010

Shuangyashan
 Location: Heilongjiang
Operator: Guodian Shuangyashan Power Generation Co Ltd
Configuration: 2 X 200 MW, 2 X 210 MW
Operation: 1988-1992
Fuel: bituminous coal
Boiler supplier: Harbin, Taganrog
T/G supplier: Harbin, LMZ, Electrosila
EPC: Harbin
Quick facts: This was the largest power stationin the province when completed. Two 600-MW units are being added to this site.

Photograph courtesy of Fubang Technology Industrial
Posted 5 Jul 2009

Xinxiang Baoshan
Location: Henan
Operator: Huadian Power International
Configuration: 2 X 660 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler Co
T/G supplier: ??
EPC: SEPCO, Henan No 1 Thermal Power Co
Quick facts: Unit-1 went commercial on 31 Mar 2007 and Unit-2 on 22 Aug 2007.

Photograph courtesy of Huadian Power Internaional
Posted 26 May 2010

Xinxiang Yuxin
Location: Henan
Operator: China Power Investment Corp
Configuration: 2 X 300 MW CHP
Operation: 2006
Fuel: coal
Boiler supplier: Wuhan
T/G supplier: Shanghai
Quick facts: These units have wet limestone scrubbers from CPI Yuanda.

Photograph courtesy of CPI Yuanda Environmental
Posted 30 Dec 2007

   
 

Yahekou-I
Location: Henan
Operator: Nanyang Yahekou Electric Power Co Ltd
Configuration: 2 X 350 MW
Operation: 1998-1999
Fuel: bituminous coal
Boiler supplier: Babock & Wilcox Espanola
T/G supplier: ABB
EPC: INITEC, China Machine New Energy Co, Henan Lixin Power Construction Supervision
Quick facts: In Nov 1998, the first 350-MW unit at the Yahekou plant went into service in Nanyang City, southwestern Henan. The second followed in Jun 1999. The Spanish government made $372mn in loans to support the project. The plant is mainly invested by Henan Construction Investment and Investment. In 2005, a second phase with two 600-MW units was launched and these came online in 2008.

Photograph courtesy of Zhengzhou Electric Power College of Power Engineering
Posted 28 Aug 2011

 

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 28-Aug-2011

Home