Datang Fuzhou
Location: Jiangxi
Operator: Datang International Fuzhou Power Generation Corp JV
Configuration: 2 X 1,000 MW
Operation: 2015-2016
Fuel: coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Guangdong Electric Power Design Institute, Tianjin Electric Power Construction Co
Quick facts: Datang Fuzhou is in Linchucan District, Fuzhou City. The USC project was approved by the NRDC on 9 Jul 2013 and started construction on 23 Feb 2014. Unit-1 finished its 168hr test run on 29 Dec 2015. The plant connects to the Fuzhou 500kV Substation.

Photograph courtesy of Dongfang Steam Turbine Co Ltd
Posted 31 Dec 2015

Huaneng Anyuan 3&4
Location: Jiangxi
Operator: Huadian Power International Corp Ltd
Configuration: 2 X 660 MW
Operation: 2015
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Jiangxi Elec Power Research & Design Inst, Zhejiang No 2 Thermal Power Const, Henan No 2 Thermal Power Const, Northeast Elec Power No 3 Eng Const, Jiangxi Thermal Power Const
Quick facts: These are China's first USC, double-reheat units with steam conditions of 310 bar/600C/620C/620C. The plant had two 125-MW sets and was formerly known as Pingxiang, and was acquired by HPI from Jiangxi Invesment Corp in Oct 2008. Construction on the second phase began on 28 Mar 2013. Unit-1 went commercial on 30 Jun 2015 and Unit-2 followed on 24 Aug 2015.

Photograph courtesy of Dongfang Steam Turbine Co Ltd
Posted 30 Dec 2015

Huangjinbu
Location: Jiangxi
Operator: China Guodian Group Corp
Configuration: 2 X 650 MW
Operation: 2007
Fuel: coal
Boiler supplier: Dongfang
T/G supplier: Shanghai
Quick facts: This plant is in Yugan County, Shangrao City, and is jointly invested by China Guodian (51%) and Huainan Mining (Group) Co Ltd (49%). Construction started on 29 Jul 2004 and Unit-1 went commercial on 15 Mar 2007, followed by Unit-2 on 31 Jul 2007. The plant connects to the local 500kV grid. Two 1,000-MW sets are in planning.

Photograph by zxw0721 (Panoramio)
Posted 9 Jul 2010

 
Jiujiang-3
Location: Jiangxi
Operator: China Guodian Group Corp
Configuration: 2 X 350 MW
Operation: 2002-2003
Fuel: anthracite and bituminous coal
Boiler supplier: Foster Wheeler, Shanghai Boiler
T/G supplier: Hitachi
EPC: Stone & Webster, Henan Lixin Power Construction Supervision
Quick facts: These are arch-fired boilers specially designed for low-volatile fuels.

Photograph courtesy of Foster Wheeler
Posted 20 Feb 2008

  Xinchang
Location: Jiangxi
Operator: Jiangxi CPI Xinchang Power Generation Co Ltd
Configuration: 2 X 700 MW
Operation: 2009-2010
Fuel: anthracite coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Central Southern China Electric Power Design Institute, Beijing Electric Power Construction Co
Quick facts: In March 2008, J-Power, China Power Investment Corp, and Shenzhen Nanshan Power Station Co Ltd (NSRD) agreed to proceed with joint development for the Xinchang power plant in Nanchang City. This was China’s first USC project jointly developed with a foreign company. The RMB 5bn project was planned for joint investment by CPI 60%, NSRD 30%, and J-Power 10%. In 2011, NSRD sold its stake to CPI. Unit-1 went commercial on 14 Dec 2009 and Unit-2 on 14 Feb 2010. On 22 Jun 2009, Jiangxi Development and Reform Commission approved  the pre-feasibility report on the expansion project of Xinchang PP with 2 X 1,000-MW USC units.

Photograph courtesy of www.cnerent.com
Posted 20 Jan 2014