|
Bellary
Location: Karnataka
Operator: Karnataka Power Corp Ltd
Configuration: 1 X 500 MW
Operation: 2008
Fuel: coal
Boiler supplier: BHEL
T/G supplier: BHEL
EPC: BHEL
Quick facts: The first 500-MW unit of BTPS cost Rs 2,120 crore and was
commissioned on 3 Nov 2008 at the site near Kudatini Village, 22km from
Bellary. The unit zero date was 29 Dec 2003. Estimated cost of power is Rs
2.20/kWh and annual generation is expected by be about 3,500 GWh. The unit connects to the 400kV grid at Davangere Substation. The stack is 275m
tall. Fuel is from a captive block of Western Coal Fields Ltd.
Photograph courtesy of Karnataka Power Corp Ltd
Posted 8 Nov 2008 |
Raichur
Location: Karnataka
Operator: Karnataka Power Corp Ltd
Configuration: 7 X 210 MW
Operation: 1985-2003
Fuel: coal
Boiler supplier: BHEL
T/G supplier: Shanghai, BHEL, Siemens
EPC: TCE Consulting Engineers, Mysore
Construction, Gammon India
Quick facts: Raichur was developed per a 1978 MOU with TCE
Consulting Engineers who were consultants for the first two stages. The
300ha site is on the Krishna River in Raichur Dist about 500km from
Bangalore. Unit-1 was completed in Mar 1985 and Unit-2 a year later.
Construction of Unit-3 was started in 1986 and completed in Mar 1991 while
Unit-4 was started in 1989 and completed in Sep 1994 These four units cost
about Rs 13,860mn. In 1996, three more units were started and these cost
Rs 15,450mn. Unit-7 was completed in a then-record 25mos at the end of
2002. An eighth 250-MW set is under construction and two 500-MW units are
planned. About 7mn tpy of coal is delivered from Singareni Collieries,
Western Coalfields Ltd. and Mahanadi Coalfields Ltd and station output is
about 10 TWh/yr, up to 40% of the state’s electricity requirement. Unit-4
was financed by Japan’s ODA.
Photograph courtesy of Gammon India Ltd
Posted 15 Nov 2008 |
Ratnagiri
Location: Karnataka
Operator: JSW Energy Ltd
Configuration: 4 X 300 MW
Operation: 2010
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: Shanghai
EPC: EDAC Engineering, SEW Constructions, Sunil HiTech Engineers
Quick facts: In Aug 2007, JSW Energy closed on Ratnagiri Phase-I in
Ratnagiri district. This Rs4,500cr project will burn about 4.1mn tpy of
imported coal. Power evacuation will be via two 400kV lines to Koyna and
two more to Karad. MOEF clearance was received in Nov 2007. Unit-1 went
commercial on 1 Sep 2010.
Photograph courtesy of JSW Energy Ltd
Posted 3 Apr 2010 |
|
|
Udupi
Location: Karnataka
Operator: Lanco Group
Configuration: 2 X 600 MW
Operation: 2010-2011
Fuel: coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Tata Consulting Engineers, Lanco
Quick facts: In April 1999, Nagarjuna Power Corp received TEC for a pair
of 500-MW coal-fired units at Nandikur, Udupi district, not far from
Mangalore. In Oct 2003, EPC tenders were received and opened, but the
project went nowhere for almost three more years. In May 2006, Lanco Group
acquired a 74% stake in the project and, shortly thereafter, a BTG order
was awarded to Dongfang for two 600-MW units in place of two 507-MW units
originally ordered from BHEL. Financial close was in Oct 2006 with a
consortium of 14 banks and financial institutions with PFC acting as the
lead arranger. In Dec 2007, Lanco terminated BHEL’s EPC contract and took
over the work itself, retaining TCE to assist. Unit-1 was synchronized on
3 Jun 2010 followed by Unit-2 in Mar 2011. Unit-2 was commissioned on 13
Jul. At that time, however, the association transmission system was not
yet complete.
Photograph by Hameed Padubidri (www.nammapadubidri.com)
Posted 2 Apr 2011 |
|