|
Bukit Asam
Location: South Sumatra
Operator: PT PLN
Configuration: 4 X 65 MW
Operation: 1989-1995
Fuel: subbituminous coal, oil Boiler supplier: Stein
T/G supplier: Rateau, GEC-Alsthom
EPC: Sogeah, Japan Jurong Engineering
Photograph courtesy of PT Bukit Asam Batubara
Posted 2 Nov 2005 |
Cilacap
Location: Central Java
Operator: PT Indonesia Power
Configuration: 2 X 300 MW
Operation: 2006
Fuel: subbituminous coal Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Chengda Engineering, Southwest Electric Power Design Institute
Quick facts: The plant is owned by PT Sumber Segara Primadya (S2P) formed
by PT PLN subsidiary PT Pembangkitan Jawa-Bali (PJB) and PT Sumberenergi
Sakti Prima (SSP). Ground breaking was on 29 December 2003 and physical
construction got underway in April 2004. The units were completed 3mos
ahead of schedule in Apr and Sep 2006, respectively. The plant cost $510mn
and sells electricity to PLN at 4.57 cents/kWh. Chengda obtained $408mn in
loans from Chinese banks while PT S2P received $200mn worth of letters of
credit from BKPM. This was the first large-scale Indonesian power plant
completed since the 1997-98 financial crisis. Black & Veatch was owner’s engineer.
Photograph courtesy of Southwest Electric Power Design
Institute
Re-posted 30 Apr 2008 |
Indramayu
Location: West Java
Operator: PT PLN Persero
Configuration: 3 X 330 MW
Fuel: coal
Operation: 2010
Boiler supplier: Babcock & Wilcox Beijing Co
T/G supplier: Beijing Beizhong
EPC: China National Electric Equipment Corp, China National Machinery
Industry Corp
Quick facts: This is part of PLN's 10-GW fast-track power expansion plan
Photograph courtesy of China National Electric Equipment Corp
Posted 17 Apr 2010
|
|
Ombilin
Location: West Sumatra
Operator: PT PLN
Configuration: 2 X 100 MW
Operation: 1996-1997
Fuel: subbituminous coal, oil Boiler supplier: Stein
T/G supplier: GEC-Alsthom
EPC: GEC-Alstom, Cegelec, Lahmeyer
Quick facts: EPC contract awarded in late 1993. ESPs from Walther.
Photograph courtesy of PT Bukit Asam Batubara
Posted 2 Nov 2005 |
Paiton I & II
Location: East Java
Operator: PT Paiton Energy / PT Jawa Power
Configuration: 2 X 670 MW, 2 X 610 MW
Operation: 1999-2000
Fuel: subbituminous coal Boiler supplier: ABB
T/G supplier: GE, Siemens
EPC: Duke/Fluor, Toyo Engineering, Black & Veatch, ABB, Siemens
Quick facts: In Mar 1993,
the government approved plans to build Paiton I – the country’s
first major IPP – but financial close was not achieved until Apr 1995.
PT Paiton Energy, the development consortium, was initially composed of
Mitsui, Edison Mission Energy, General
Electric, and PT Batu Hitam Perkasa. The sponsors provided
$680mn while the balance of $1.82bn project cost was financed by Chase Manhattan and the Industrial Bank
of Japan, and the U.S. and Japanese EXIM banks. OPIC provided $200mn in
investment guarantees. The PT Jawa Power consortium for Paiton II was led by Siemens and England’s
PowerGen (now E.ON UK) and included local partner PT Bumipertiwi
Tatapradipta, a subsidiary of Bimantara Group. Financing for the $1.65bn
plant was arranged in Mar 1996 with debt totaling $1.36bn from export
credit agencies Hermes ($500mn), the U.S. EXIM
($400mn), KfW ($250mn), and $200mn from the private placement of senior
notes. In May 2004, YTL Power acquired a 35% stake in PT Jawa Power
for $139.4mn. Both Paiton I
and Paiton II have Alstom saltwater FGD scrubbers.
Photograph courtesy of Siemens AG
Posted 9 Feb 2002 |
Paiton PLN
Location: East Java
Operator: PT PLN
Configuration: 2 X 400 MW
Operation: 1993-1994
Fuel: subbituminous coal Boiler supplier: ABB
T/G supplier: Toshiba
EPC: Sargent & Lundy, Hyundai
Quick facts: In Feb 2007, Harbin signed a contract to supply a 660-MW unit
to PLTU Paiton for service in 2009.
Photograph by John Kirkby
Posted 20 Apr 2008 |
|
|
Tanjung Jati-B
Location: Central Java
Operator: PT Central Java Power
Configuration: 2 X 660 MW
Operation: 2006
Fuel: subbituminous coal Boiler supplier: B&W
T/G supplier: Toshiba
EPC: Sumitomo, Black & Veatch, SNC Lavalin, ESB International, Eskom
Enterprises
Quick facts: Tanjung Jati-B was proposed by Hopewell Holdings and initially bid
as an IPP in Jun 1994. A PPA with PLN followed in Sep 1994.
The EPC contract was signed in Sep 1995 and site work started on 15 Apr
1997. The Asian financial crisis combined with allegations about
mismanagement of the PPA terms led to
Hopewell withdrawing, leaving the project about one-third complete.
Sumitomo renegotiated the development as a leasing scheme and construction
resumed in Sep 2003 with financing from JBIC. The 5yr project suspension
led to parts and equipment being stored onsite and at 75 locations worldwide.
B&W supplied cold-side ESPs and a wet limestone FGD system using
seawater makeup. The APC systems exhaust
through a 240m
stack. Coal is received at a 1,368m jetty equipped with two 1,500 tph
unloaders built by PT Decorient Indonesia and Interbeton bv. The plant cost $904mn. Two
additional units were agreed in Nov 2008 and are being built for service
in 2012. PT Central Jawa Power is a 100% Sumitomo subsidiary.
Photograph courtesy of
Sumitomo
Posted 18 Mar 2009 |
|