Coal-Fired Power Plants in Indonesia - other islands
Amurang
Location: North Sulawesi
Operator: PT PLN Persero
Configuration: 2 X 25 MW
Fuel: lignite
Operation: 2012
Boiler supplier: China Western Power Industrial
T/G supplier: Qingdao Jieneng
EPC: PT Wijaya Karya
Quick facts: In Jun 2008, construction got underway on this CFB plant in Kec Amurang, Kab Minahasa Selatan. The FTP-1 units were turned over on 9 Oct and 20 Nov 2012, respectively, and cost an estimated Rp 647bn. Fuel burn is about 350,000 tpy.

Photograph courtesy of wikimapia
Posted 21 Dec 2014

Barru
Location: South Sulawesi
Operator: PT PLN Persero
Configuration: 2 X 50 MW
Fuel: coal
Operation: 2013
Boiler supplier: Hangzhou
T/G supplier: Nanjing
EPC: Hubei Hongyuan Power Engineering Co Ltd, PT Bagus Karya, PT Gemilang Pratama Karya
Quick facts: Emerson supplied an Ovation control system for PLTU Labuanm Banten. The first unit was connected in Jul 2009 and officially opened by President Susilo Bambang Yudhoyono on 28 Jan 2010, but the plant did not go into full commercial service until 2013.

Photograph courtesy of PT PLN
Posted 12 Aug 2012

Galang Batang
Location: Riau
Operator: PT PLN Persero
Configuration: 2 X 15 MW
Fuel: coal
Operation: 2012
Boiler supplier: Takuma
T/G supplier: GEC-Alstom
EPC: Capital Turbine
Quick facts: This is the only coal-fired TTP on Bintan Island.

Photograph courtesy by rudi@prismatic.asia (Panoramio)
Posted 29 Mar 2015

Kaltim Teluk Balikpapan
Location: East Kalimantan
Operator: PT PLN
Configuration: 2 X 110 MW
Operation: 2016
Fuel: coal
Boiler supplier: Wuxi
T/G supplier: ??
EPC: PT Adhu Karya, Sinohydro, Hunan Electric Power Construction
Quick facts: In Dec 2010, a consortium of PT Adhu Karya and Sinohydro Corp was awarded the EPC contract for PLN’s Kaltim Teluk Balikpapan CFB project in Desa Kariangau, Kec Balikpapan Barat. Construction began in Mar 2011 and the units were initially scheduled online in Jun and Sep 2013, respectively. Unit-1 was synchronized on 24 Nov 2015. The FTP-1 project represents an investment of Rp 2.5tn.

Photograph courtesy of Sepco No 3 Huafeng
Posted 20 Feb 2016

Nagan Raya
Location: Aceh
Operator: PT PLN
Configuration: 2 X 110 MW
Operation: 2013-2014
Fuel: coal
Boiler supplier: Wuxi
T/G supplier: Nanjing
EPC: Sinohydro, Sinohydro No 8, Northwest Power Construction Group Corp
Quick facts: Nagan Raya is at Suak Puntong Village, Kuala District, Nagan Raya Regency. The kickoff meeting was held on on 8 May 2008, the first pile was driven on 25 Nov. It was a $247mn contract for Sinohydro.

Photograph courtesy of PT PLN
Posted 25 Jan 2014

Palu
Location: Central Sulawesi
Operator: PT Pusaka Jaya Palu Power
Configuration: 2 X 15 MW
Operation: 2006
Fuel: coal
Boiler supplier: Wuxi
T/G supplier: Qingdao, Jinan
EPC: SEPCO No 3
Quick facts: This is an IPP project of PT Toba Sejahtera. Coal is supplied by PT PLN via barge from East Kalimantan.

Photograph courtesy of SEPCO No 3
Posted 6 Nov 2011

Punagaya
Location: South Sulawesi
Operator: PT Bosowa Makassar
Configuration: 2 X 125 MW
Operation: 2012
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
EPC: Chengda, Southwest Electric Power Design Institute, Wika
Quick facts: In Nov 2010, local industrial and infrastructure conglomerate PT Bosowa Corp began construction on this IPP at Pungaya, Bangkala, Kab Jeneponto. The project was completed by SPV PT Bosowa Makassar at a cost of about $250mn with China’s Chengda acting as lead EPC contractor. Bosowa has a 200-MW PPA with PLN for the Phase-I plant at US 5.5 cents/kWh excluding fuel costs. The project took only 19mos to complete according to the owner, a substantial improvement over the original 30mo schedule.

Photograph courtesy of ekonomi.inilah.com
Posted 12 Sep 2012

Riau Tenayan
Location: Riau
Operator: PT PLN Persero
Configuration: 2 X 110 MW
Fuel: coal
Operation: 2015
Boiler supplier: ??
T/G supplier: ??
EPC: PT Rekayasa Industri, Hubei Hongyuan Power Engineering Co Ltd
Quick facts: Commissioning of this TPP was transmission-constratined.

Photograph courtesy of Hubei Hongyuan Power Engineering Co Ltd
Posted 10 Jan 2015

Tanjung Tabalong
Location: South Kalimantan
Operator: PT Adaro Energy Tbk
Configuration: 2 X 30 MW
Operation: 2013
Fuel: subbituminous coal
Boiler supplier: BHEL
T/G supplier: Siemens
EPC: Punj Llyod, International Development and Engineering Associates
Quick facts: This power station is associated with the largest single-site coal mine in the southern hemishpere, located in Tabalong and Balangan districts. Annual production is on the order of 40mn typy of ultra low-sulfur, moderate CV subbituminous coal. The new TPP replaces a 20-MW diesel plant. Electricity will be used to power the converyor system and other mine and handling infrastructure as well as the local grid. The development company is Adaro subsidiary PT Makmur Sejahtera Wisesa (MSW). The project cost about $160mn. Fuel burn is expected to be about 300,000 tpy.

Photograph courtesy of sarabakawa.com
Re-posted 18 May 2014

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 24-Apr-2016

Home