Wind Energy Power Plants in the UK - offshore
![]() |
![]() |
![]() |
|
Beatrice Field Location: Offshore Ross-shire Operator: Talisman Energy (UK) Ltd Configuration: 2 X 5-MW 5M Operation: 2007 WTG supplier: REpower EPC: AMEC, REpower Quick facts: In Apr 2005, Talisman Energy and Scottish and Southern awarded AMEC a contract to design and manage delivery of two 5-MW wind turbines for the Beatrice wind farm demonstration project. The scheme demonstrates the feasibility of siting WTGs in deepwater (45m in this instance) at a site 25km offshore and 70km northeast of Inverness in the Beatrice oil field. The first WTG was set in August 2006 and came online in May 2007 with the second following in Aug. Photograph courtesy of REpower Systems AG |
Blyth Offshore Location: Northumberland Operator: AMEC Border Wind Configuration: 2 X 2-MW V66 Operation: 2000 WTG supplier: Vestas Quick facts: These were the first truly offshore WTGs installed in the UK. Photograph courtesy of AMEC Border Wind |
Burbo Bank Location: Lancashire Operator: Dong (UK) Ltd Configuration: 25 X 3.6-MW SWT-3.6-107 Operation: 2007 WTG supplier: Siemens Wind Quick facts: These machines were erected in less than 1.5mos at a site 12km offshore Wallasey in Liverpool Bay, well ahead of schedule. During construction, Siemens leased a 45,000 mē site at Mostyn in North Wales. The 65m steel towers were assembled upright and all systems were tested before they were loaded onto the installation vessel which carried towers, nacelles, hubs and blades for 3 turbines per trip to the site area. Each 500t wind turbine was erected in five heavy lifts with a maximum weight of approximately 185t. The average erection time per turbine was less than half a day. Photograph courtesy of Siemens |
![]() |
![]() |
![]() |
|
Greater Gabbard Location: Suffolk Operator: Airtricity Holdings Ltd Configuration: 140 X 3.6-MW SWT-3.6-107 Operation: 2010 WTG supplier: Siemens Wind Power EPC: Fluor Quick facts: Greater Gabbard was completed in Sep 2012 and became the largest offshore winfarm in the world. It is a 50:50 joint venure of Airtricity Holdings (SSE) and RWE npower renewables. The site is 25km offshore the Suffolk coast and is connected via 3 main subsea cables to a 132kV substation at Sizewell. Photograph courtesy of RWE npower renewables |
Gunfleet Sands Location: Norfolk Operator: Dong Energy UK Configuration: 48 X 3.6-MW SWT-3.6-107 Operation: 2010 WTG supplier: Siemens Wind Power EPC: Dong Energy, MT Højgaard Quick facts: Gunfleet Sands is 7km off the Essex coast opposite Clacton-on-Sea and the subsea cable connection makes landfall just northeast of Holland-on-Sea. The project was first identified in 1996 by Windmaster Developments, acquired by Enron in 2000, purchased by GE in 2002, and then purchased by Dong Energy. Final consents were awarded in Mar 2004 for Phase-I and in Mar 2008 for Phase-II. The turbines are spaced a 435m and the turbine rows are about 890m apart. The total surface area of the site is approximately 15km². The maximum height of the blade tip above sea level is 129m. Due to the very varying water depths the installation was carried out by the use of the large floating crane "Svanen" and the jack-up barge "Excalibur". Photograph courtesy of Osprey Shipping Ltd |
Kentish Flats Location: Norfolk Operator: Dong Energy UK Configuration: 30 X 3-MW V90 Operation: 2005 WTG supplier: Vestas Quick facts: At completion, this was the largest offshore wind farm in the U.K. and the V90 machines are the largest built in the British Isles as well. Kentish Flats is expected to produce 285 GWh/yr of electricity. Photograph courtesy of Elsam |
![]() |
![]() |
![]() |
|
Lincs Offshore Location: Lincolnshire Operator: Lincs Wind Farm Ltd Configuration: 75 X 3.6-MW SWT-3.6-120 Operation: 2013 WTG supplier: Siemens Wind Power EPC: Rambøll Danmark A/S, ISC Consulting Engineers A/S, MT Højgaard Quick facts: The final WTG at Lincs Offshore was installed on 31 Mar 2013. The site is 8km off the coast of Skegness in water depths of 8.5 to 16.3m. Construction was staged from Esbjerg, Denmark. The monopiles weighed from 320-480t. Lincs Wind Farm is a JV of Centrica Energy, DONG Energy and Siemens Project Ventures. Photograph courtesy of Centrica |
London Array Offshore Photograph courtesy of London Array Ltd |
Lynn/Inner Dowsing Photograph courtesy of Centrica |
![]() |
![]() |
![]() |
| North Hoyle Location: Offshore Flintshire Operator: RWE npower Renewables Configuration: 30 X 2-MW V80 Operation: 2004 WTG supplier: Vestas Photograph courtesy of and copyright by National Wind Power |
Robin Rigg Location: Dumfries and Galloway Operator: E.ON UK Renewables Ltd Configuration: 60 X 3 MW V90 Operation: 2010 WTG supplier: Vestas EPC: Vestas, MT Hojgaard Quick facts: Robin Rigg was commissioned on 16 Apr 2010 as the largest operating offshore wind park in the UK. The project was acquired by E.ON UK Renewables in autumn 2003. The site is in Solvay firth is 9km off Balcary Point and about the same distance from Seaton, Cumbria, where the transmission cables make landfall. The turnkey construction contract was awarded in Dec 2006. Robin Rigg cost about €500mn. Photograph courtesy of E.ON UK |
Rhyl Flats Location: Caernarfonshire (Wales) Operator: RWE npower renewables Configuration: 25 X 3.6-MW SWT-3.6-107 Operation: 2009 WTG supplier: Siemens Wind Power EPC: Rambøll A/S, MT Højgaard Quick facts: Rhyl Flats was built offshore Abergele, North Wales, in water depths of 6.5 to 12.5m. The design and fabrication of the foundations took place during the second half of 2007, and installation of the foundations was carried out during the spring/summer of 2008. Photograph courtesy of RWE |
![]() |
![]() |
|
Scroby Sands Photograph courtesy of and copyright by E.ON UK |
Thanet Photograph courtesy of Vattenfall |
|
![]() |
||
Data: industcards, Platts UDI World Electric Power Plants Data Base
Updated 17-Apr-2013