Wind Energy Power Plants in the UK - offshore
|
|
|
|
|
Beatrice Field Location: Offshore Ross-shire Operator: Talisman Energy (UK) Ltd Configuration: 2 X 5-MW 5M Operation: 2007 WTG supplier: REpower EPC: AMEC, REpower Quick facts: In Apr 2005, Talisman Energy and Scottish and Southern awarded AMEC a contract to design and manage delivery of two 5-MW wind turbines for the Beatrice wind farm demonstration project. The scheme demonstrates the feasibility of siting WTGs in deepwater (45m in this instance) at a site 25km offshore and 70km northeast of Inverness in the Beatrice oil field. The first WTG was set in August 2006 and came online in May 2007 with the second following in Aug. Photograph courtesy of
REpower Systems AG |
Blyth Offshore Location: Northumberland Operator: AMEC Border Wind Configuration: 2 X 2-MW V66 Operation: 2000 WTG supplier: Vestas Quick facts: These were the first truly offshore WTGs installed in the UK.
Photograph courtesy of AMEC Border Wind
|
Burbo Bank Location: Lancashire Operator: Dong (UK) Ltd Configuration: 25 X 3.6-MW 3.6/107 Operation: 2007 WTG supplier: Siemens Wind Quick facts: These machines were erected in less than 1.5mos at a site 12km offshore Wallasey in Liverpool Bay, well ahead of schedule. During construction, Siemens leased a 45,000 m² site at Mostyn in North Wales. The 65m steel towers were assembled upright and all systems were tested before they were loaded onto the installation vessel which carried towers, nacelles, hubs and blades for 3 turbines per trip to the site area. Each 500t wind turbine was erected in five heavy lifts with a maximum weight of approximately 185t. The average erection time per turbine was less than half a day. Photograph courtesy of
Siemens |
![]() |
![]() |
![]() |
|
Gunfleet Sands Location: Norfolk Operator: Dong Energy UK Configuration: 48 X 3.6-MW SWT-3.6-107 Operation: 2010 WTG supplier: Siemens Wind Power EPC: Dong Energy, MT Højgaard Quick facts: Gunfleet Sands is 7km off the Essex coast opposite Clacton-on-Sea and the subsea cable connection makes landfall just northeast of Holland-on-Sea. The project was first identified in 1996 by Windmaster Developments, acquired by Enron in 2000, purchased by GE in 2002, and then purchased by Dong Energy. Final consents were awarded in Mar 2004 for Phase-I and in Mar 2008 for Phase-II. The turbines are spaced a 435m and the turbine rows are about 890m apart. The total surface area of the site is approximately 15km². The maximum height of the blade tip above sea level is 129m. Due to the very varying water depths the installation was carried out by the use of the large floating crane "Svanen" and the jack-up barge "Excalibur". Photograph courtesy of Osprey Shipping Ltd |
Kentish Flats Location: Norfolk Operator: Dong Energy UK Configuration: 30 X 3-MW V90 Operation: 2005 WTG supplier: Vestas Quick facts: At completion, this was the largest offshore wind farm in the U.K. and the V90 machines are the largest built in the British Isles as well. Kentish Flats is expected to produce 285 GWh/yr of electricity.
Photograph courtesy of Elsam |
Lynn/Inner Dowsing Location: Lincolnshire Operator: Centrica Energy Configuration: 54 X 3.6-MW SWT-3.6-107 Operation: 2008 WTG supplier: Siemens EPC: RES Quick facts: The Lynn complex is 5.2km offshore Skegness while Inner Dowsing is 5.2km offshore Ingoldmells. The concessions were acquired by Centrica from RES in Dec 2003 and construction tenders issued in 2006. The final contracts were awarded in Feb 2007 for the offshore and onshore work, including a new substations in Skegness. First power to the grid was in May 2008 and the last machine was installed the following month. Nexans supplied 72km of 36kV HV submarine cable. The projects cost around £300m and Ode was owner's consultant. Photograph courtesy of
Centrica |
![]() |
![]() |
![]() |
|
North Hoyle Location: Offshore Flintshire Operator: npower Renewables Configuration: 30 X 2-MW V80 Operation: 2004 WTG supplier: Vestas Photograph courtesy of and copyright by National Wind
Power
|
Robin Rigg Location: Dumfries and Galloway Operator: E.ON UK Renewables Ltd Configuration: 60 X 3 MW V90 Operation: 2010 WTG supplier: Vestas EPC: Vestas, MT Hojgaard Quick facts: Robin Rigg was commissioned on 16 Apr 2010 as the largest operating offshore wind park in the UK. The project was acquired by E.ON UK Renewables in autumn 2003. The site is in Solvay firth is 9km off Balcary Point and about the same distance from Seaton, Cumbria, where the transmission cables make landfall. The turnkey construction contract was awarded in Dec 2006. Robin Rigg cost about €500mn.
Photograph courtesy of E.ON UK |
Scroby Sands Location: Norfolk Operator: E.ON UK Renewables Configuration: 30 X 2-MW V80 Operation: 2004 WTG supplier: Vestas Quick facts: The Scroby Sands wind farm is in the North Sea, 2.5km off the coast of Great Yarmouth. The 60m turbines are on hollow 4.5m steel towers in from 13 to 20m of water. The tower foundations were piled up to 30m into the sea bed. Photograph courtesy of and copyright by E.ON UK |
![]() |
||
|
Thanet Location: Ofshore Kent Operator: Vattenfall Wind Configuration: 100 X 3-MW V90 Operation: 2010 WTG supplier: Vestas EPC: Vestas, Vattenfall, A2SEA Quick facts: When officially opened on 23 Sep 2010, Thanet was the world's largest offshore wind farm. The installation is in the English Channel about 11km offshore Margate. Thanet took 2yrs to build and cost about €880mn. The towers are up to 115m tall and are placed in 10-25m of water over a 35km² site. Two subsea cables manufacture by Prysmian Group connect to an onshore substation at Richborough and this connects to the 132kV grid.
Photograph courtesy of Vattenfall |
||
![]() |
||
Data: industcards, Platts UDI World Electric Power Plants Data Base
Updated 01/12/11