Waste-to-Energy Plants Elsewhere
Baku WTE
Location: Azerbaijan
Operator: CNIM Azerbaycan Ltd
Configuration: 1 X 37 MW
Operation: 2012
Fuel: refuse
Boiler/incinerator supplier: Martin, CNIM
T/G supplier: Siemens
EPC: CNIM, Ustay Group
Quick facts: The Baku EFW project was iniaiated in Mar 2006 and a formal request was recevied from Ministry of Economic Development in Sep 2006 to proecsss 500,000 tpy of MSW. In Jan 2007, a project MOU was signed between CNIM and MED and the turnkey, €346mn DBO contract signed on 15 Dec 2008. Site prep began in Jun 2009, the foundation stone was laid in Nov 2009, and the plant was opened by President Ilham Aliyev on 19 Dec 2012. The 2-line plant is on a 20ha site in Balakhani settlement and is expected to produce 231,500 MWH/yr. The plant is ownd by state-enterprise Tamiz Shahar JSC.

Photograph by Erhan Sulu (Panoramio)
Posted 6 Feb 2013

Burnaby
Location: Canada
Operator: Covanta Burnaby Renewable Energy ULC
Configuration: 1 X 25 MW
Operation: 1988-2003
Fuel: refuse
Boiler/incinerator supplier: Martin, B&W
T/G supplier: Alstom
Quick facts: Burnaby is a three line, 800 tpd WTE plant owned by Metro Vancouver. The project was originally developed by Montenay Inc. The facility went commercial in Mar 1988, selling steam to a nearby paper recycling facility until its closure in 2011. A 25-MW turbogenerator was added in 2003 along with an air-cooled condenser and the plant now sells 100% of the produced electricity.

Photograph courtesy of Montenay Inc
Posted 12 Nov 2003

CACEM UTVD
Location: French West Indies
Operator: Martiniquaise de Valorisation
Configuration: 1 X 7.2 MW
Operation: 2002
Fuel: refuse
Boiler/incinerator system supplier: Vinci, CTC
T/G supplier: ??
EPC: Vinci, SDEM
Quick Facts: This facility is near Fort-de-France, Martinique, and was commissioned in Jul 2002. It is owned by CACEM (Communaute d'Agglomeration du Centre de la Martinique), but operated by a private company. Design throughput is 112,000tpy of MSW on two treatment lines.

Photograph courtesy of SDEM Entreprises
Posted 5 Oct 2008

Covanta Durham
Location: Canada
Operator: Covanta
Configuration: 1 X 20 MW
Operation: 2016
Fuel: refuse
Boiler/incinerator supplier: Anhui Jinding
T/G supplier: GE
EPC:  Sigma Energy Solutions Inc, Kenaidan Contracting Ltd, Barton Malow Canada
Quick facts: This 140,000 tpy WTE plant is in Clarington, Ontario. Notice to proceed was received in Aug 2011 and the plant went commercial in Feb 2016. Covanta has an initial 20yr O&M contract. Design MSW throughput is 140,000 tpy from the Regional Municipalities of Durham and York.

Photograph courtesy of Covanta
Re-posted 10 Feb 2016

IZAYDAS
Location: Turkey
Operator: IZAYDAS - Izmit Atik Atiklari Aritma Yakma ve Degerlendirme
Configuration: 5.2 MW CHP
Operation: 1997
Fuel: refuse
Boiler/incinerator system supplier: Lurgi
Turbine supplier: ??
Quick Facts: This was the fist mass-burn WTE plant in Turkey. It is equipped with rotary kiln technology. It is 100% owned by Kocaeli Metroploitan Municipality. Throughput is about 35,000 tpy of MSW with a small amount of hazardous waste.

Photograph courtesy of IZAYDAS - Izmit Atik Atiklari Aritma Yakma ve Degerlendirme AS
Posted 16 Nov 2014

Kyiv Energia
Location: Ukraine
Operator: Kyivenergo
Configuration: heat only
Operation: 2001
Fuel: refuse
Boiler/incinerator system supplier: CKD Dukla
Quick Facts: This is the only incinerator plant in Kyiv and can consume about one-quarter of the metro area's MSW. Heat output is not fully utilized by 13 connected cusometers and plans are in hand to add a 10-MW steam turbine along with up-to-date pollution control equipment. Another boiler and a 7-MW steam turbine are also planned. Plant throughput at that time will be 350,000 tpy.

Photograph courtesy of Kyivenergo
Posted 2 Feb 2013

La Colette
Location: Jersey
Operator: Jersey Transport and Technical Services
Configuration: 1 X 10.2 MW
Operation: 2011
Fuel: refuse
Boiler/incinerator system supplier: CNIM
Turbine supplier: ??
EPC: CNIM, Camerons Ltd, Spie Batignolles TPCI, Fichtner
Quick Facts: The £120mn La Colette EFW project (left rear) was approved on 9 Jul 2008 and construction got underway in Feb 2009. First waste was burned in Feb 2011 and the project commissioned in May 2011. This was the largest capital project ever for the States of Jersey. An existing WTE plant was closed after the new unit became fully operational.

Photograph by Danrok (wikipedia)
Re-posted 31 Jan 2015

MSZ-3
Location: Russia
Operator: OOO EVN-Ekotechprom MSZ 3
Configuration: 1 X 10.9 MW CHP
Operation: 2007
Fuel: refuse
Boiler/incinerator system supplier: Standardkessel, Podoloski
T/G supplier: TGM Kanis
EPC: Abfallverwertung Niederosterreich
Quick Facts: Construction of the MSZ-3 project started in Mar 2005 and EVN has contracted to operate the plant until 2019, after which ownership will pass to the City of Moscow. The plant has two lines and a design throughput of 360,000 tpy of municipal waste. The new plant was constructed on the site of a former waste disposal plant which, after operating for more than 20yrs, had to be dismantled almost in its entirety. Final acceptance was on 27 Sep 2007 and it was officially opened on 15 Dec 2007 by Moscow Mayor Yuri Luzkov. The total investment was about €175mn.

Photograph courtesy of EVN
Posted 1 Nov 2009

Qatar DSWMC
Location: Qatar
Operator: Keppel Seghers
Configuration: 1 X 40 MW
Operation: 2011
Fuel: refuse
Boiler/incinerator system supplier: Keppel Seghers
Turbine supplier: Siemens sro, ABB
EPC: Keppel Seghers, AMEM Qatar
Quick Facts: The Domestic Solid Waste Management Centre (DSWMC) near Mesaieed was the first integrated solid waste treatment facility in the Gulf Region. The scheme includes waste sorting and recycling facilities, a landfill, composting plant and a 3-line, 1,500 tpd incineration plant. Flue gas cleaning includes rotary atomiszrs with lime injection, activated carbon dosing, and bag filters on each line. The stack is 80m tall. The works were built on order of the Ministry of Municipal Affairs and Agriculture by the Public Works Authority.

Photograph courtesy of Keppel Seghers
Posted 21 Nov 2012

   
St-Barthelemy
Location: French West Indies
Operator: Ouanalao Environnement SA
Configuration: 1 X 4.5 MWt
Operation: 2001
Fuel: refuse
Boiler/incinerator system supplier: Bouillet
Quick Facts: St-Barthelemy is a 25 km² island north of Guadeloupe with about 7,000 inhabitants. The plant has a single line with an oscillating kiln handling 36 tpd of MSW, the island's entire output. It is coupled to a thermal seawater desalination plant run by UCDEM that is capable of supplying up to 1,350m³ per day of potable water, meeting local requirements even at the height of the tourist season.

Photograph courtesy of Groupe Tiru
Posted 7 Apr 2007